San Antonio City Code § 34-1201 Distribution mains.
Sec. 34-1201. - Distribution mains.
(a) In the event a recycled water customer desires the extension of distribution mains to provide the customer with recycled water service, the customer shall bear all costs of extending the distribution main from the transmission main to the customer's property line. The size of such distribution mains are to be determined by SAWS, in its discretion, based on the customer's expected recycled water purchases.
(b) SAWS shall review and approve the location of all recycled water distribution mains, as well as the plans and specifications for recycled water distribution mains and associated improvements including without limitation, pumps, monitoring devices and storage facilities. All construction of distribution mains shall be performed by the customer or a contractor selected by the customer, provided, however, that the customer or contractor shall furnish a performance bond, executed by a corporate security authorized to do business in the state and maintaining an agent in Bexar County upon whom service of citation may be had. Such performance bond shall be in an amount equal to the total construction cost under the contract. The bond shall be in favor of SAWS and the customer and shall assure (1) completion of all construction required under the contract in full conformity with the plans and specifications approved by SAWS; (2) maintenance of such construction for a period of at least ninety (90) days after acceptance of construction by SAWS; and (3) payment in full by contractor of all subcontractors and materialmen providing labor and/or material in connection with the construction of the distribution main. All construction work on the distribution main shall be subject to inspection by city and SAWS officials and representatives. In no event shall any portion of any distribution main installed in an excavation be covered over unless and until it has been inspected and approved by SAWS.
(c) Upon completion of construction of a recycled water distribution main and receipt of evidence acceptable to SAWS that all costs and fees for construction of the distribution main have been paid in full and all liens released, SAWS shall issue a written certificate of acceptance of the specific distribution main by SAWS, whereupon the distribution main covered by the acceptance certificate shall be the property of SAWS.
(Ord. No. 87597, § 1, 3-26-98)