El Paso City Code § 19.04.010 Purpose, applicability, exceptions and effect.
19.04.010 - Purpose, applicability, exceptions and effect.
A. Purpose. The purpose of a final plat is to assure that the subdivision of the land subject to the plat is consistent with all standards of this title pertaining to the adequacy of public facilities, that public improvements to serve the subdivision or development have been installed and accepted by the city or that provision for such installation has been made, that all other requirements and conditions have been satisfied or provided for to allow the plat to be recorded, to assure that the subdivision meets all other standards of this title and to enable initiation of site preparation activities for any lot or tract subject to the final plat. The city will not require non-engineering related significant changes in the final subdivision improvement plans or final plat approval that contradict the preliminary plat approval, reserving the right to address life safety or other significant issues that should have been addressed in the preliminary plat.
B. Applicability. Construction of public improvements may occur prior to final plat approval if the requirements in Chapter 19.08 are met. Prior to submission of the final plat application for approval, the final subdivision improvement plans, including water and wastewater plans, even though provided by another design agency, other public utilities and storm drainage, must be submitted to the planning division. In order to construct public improvements prior to approval of the final plat, such plans, except water and wastewater when part of the EPWU or other water or wastewater system, must be reviewed and approved by the city manager, or designee. The city manager or designee may recommend that a final plat be approved subject to corrections being made to the final subdivision improvement plans.
C. Effect. Approval of a final plat shall authorize the subdivider to install any improvements in public rights-of-way with approved subdivision improvement plans and to seek approval of site preparation, building and other permits for any lot in the subdivision, in accordance with section 19.08.020. Approval also authorizes the recordation of the final plat in accordance with this title.
(Ord. 16882 § 2 (part), 2008) (Ord. No. 17236, § 27, 11-10-2009; Ord. No. 17251, § 4, 12-15-2009; Ord. No. 17396, § 5, 8-24-2010)