Permits, installation and service.
Riverside Municipal Code § 5.56.270
in effect5.56.270 - Permits, installation and service.
A. Within 30 days after acceptance of any franchise the grantee shall proceed with due diligence to obtain all necessary permits and authorizations which are required in the conduct of its business, including, but not limited to, any utility joint use attachment agreements, microwave carrier licenses, and any other permits, licenses and authorizations to be granted by duly constituted regulatory agencies having jurisdiction over the operation of CATV systems, or their associated microwave transmission facilities.
B. Within 90 days after obtaining all necessary permits, licenses and authorizations, grantee shall commence construction and installation of the CATV system.
C. Within 90 days after the commencement of construction and installation of the system, grantee shall proceed to render service to subscribers, and the completion of the construction and installation shall be pursued with reasonable diligence thereafter, so that service to all areas designated on the map accompanying the application for franchise, as provided in Sections 5.56.580 through 5.56.610, shall be provided to all grantee's licensed subscribers within such time and upon such conditions as shall be determined by the City Council.
D. Failure to do any of the foregoing shall be grounds for a termination of the franchise.
E. The City Manager may extend the time for obtaining necessary permits and authorizations and for beginning construction and installation for additional periods in the event the grantee acting in good faith experiences delays by reason of circumstances beyond his control.
(Ord. 7387 § 4, 2017)
Source: City of Riverside, California, Municipal Code and City Charter (Municode Library, library.municode.com)URL: https://library.municode.com/ca/riverside/codes/code_of_ordinances?nodeId=PTIICOOR_TIT5BU_CH5.56CAFR_5.56.270PEINSEFetched: 11/1/2026