Premium large commercial and industrial primary electric service, Schedule "LCI-PP" (Rate 23PP).
Columbus City Codes § 1163.077
in effect1163.077 - Premium large commercial and industrial primary electric service, Schedule "LCI-PP" (Rate 23PP).
A. Available for general light and power use to the customers generally establishing maximum demand in excess of fifty (50) KW.
B. Type of Service:
1. Alternating current, sixty (60) hertz, delivered from the city's electric distribution system at nominal voltages of 2300, 7200, 13,200, 13,800, and 14,400 volts, three-phase.
2. Service of at least one (1) of the foregoing characteristics shall be available to a customer, the particular service characteristics to be at the option of the city.
C. Rates:
1. Customer charge: $155.08
2. Demand charge: $16.26 per kW
3. Energy charge: $0.08926 per kWh
D. Power Cost Reserve Adjustment: The schedule of charges described in division (C) shall be adjusted in accordance with the Power Cost Reserve Adjustment as set forth in section 1163.03.
E. Minimum Charge:
1. The minimum monthly charge shall be equivalent to the applicable demand charge applied to the maximum demand, the customer charge, and any applicable energy charge and power cost reserve adjustment.
F. Delayed Payment Charge:
1. The above tariff is net if account is paid within fifteen (15) days of date of bill. On all accounts not so paid, an additional charge of five (5) percent of the total amount billed, but not less than one dollar ($1.00) will be made.
G. Determination of Maximum Demand:
1. The maximum demand shall be the sum of the individual demands of each metered service supplied under the provisions of this schedule.
2. The individual demand of each metered service shall be determined either as the measured demand or as estimated demand derived from the connected loads. At the request of a consumer whose measured demand during off-peak hours normally exceeds measured demand during on-peak hours, the city will install metering equipment to determine the measured demand during both on-peak and off-peak hours. The total installed cost of such metering equipment in excess of the cost of the metering equipment that is necessary to determine a consumer's single highest measured demand during the month will be paid for by the consumer.
3. For those consumers whose measured demand is determined during both on-peak and off-peak hours, maximum demand in any month shall be the greater of:
a. The measured demand during on-peak hours of the current month; or
b. The minimum billing demand, if any, specified in the service contract; or
c. Fifty (50) KW.
d. For all other consumers, all hours are considered as on-peak hours.
H. Excess Demand:
1. The excess demand in any month shall be the amount by which the measured demand during off-peak hours of the current month exceeds the maximum demand for the month.
I. Service and Contract Provisions:
1. Each separate point of delivery of service by one or more metered services shall be considered a contract location and shall be metered and billed under a separate service contract.
2. Only one (1) metered service of each type, as to voltage and phase, will be supplied to a consumer under this schedule at one (1) contract location. Where two (2) or more services are supplied to a consumer at one (1) contract location, said services, within the limitations above stated, may be combined in one (1) service contract under this schedule, or may be served under separate contracts under this or other applicable schedules, at the consumer's option.
J. Term of Contract:
1. Unless otherwise provided, the term of contract for service under this schedule shall not be less than one (1) year.
(Ord. No. 2132-2015, §§ 3, 6, 11-23-2015, eff. 1-1-2016; Ord. No. 2839-2024, § 10, 11-25-2024; Ord. No. 3085-2025, § 1, 11-24-2025)
Source: City of Columbus, City Codes and City Charter (Municode Library, library.municode.com)URL: https://library.municode.com/oh/columbus/codes/code_of_ordinances?nodeId=TIT11WASEELCO_CH1163MUELRA_1163.077PRLACOINPRELSESCLRA23PPFetched: 10/27/2026