4.12.060 - Form of demands—Deadline for filing.
(A) The City Council must not hear, consider, credit, audit or allow any claim in favor of any person against the City, unless the same is itemized, giving names, dates and particular services rendered, character of work done, number of days engaged, supplies or materials furnished, to whom and quantity and price to be paid therefor, and unless the same is presented to and filed with the Director of Finance within six months after the last item of the order was received or services rendered.
(B) If the City Council does not hear or consider a claim for the reason that it is not itemized or certified, the City Council shall cause notice to be given to the claimant or his attorney of that fact, and shall give time to have the same itemized and certified, provided that in no case shall such time be enlarged or given beyond the original six-month limitation mentioned above.
(Ord. 3653 § 9, 1992: Ord. 240 § 4, 1938: prior code § 1-17-7)