§ 25-1-82 - NON-SUBDIVISION APPLICATION REQUIREMENTS AND EXPIRATION.
This section does not apply to an application for preliminary plan, plat, or subdivision construction plan.
(A) The responsible director may adopt rules establishing the requirements for an application, including timelines for completing staff review and deadlines by which an application must be updated to meet the requirements of this title and other applicable regulations. The rules adopted must be consistent with the timelines for action established in Section 25-1-64 (Action on an Application; Deadline).
(B) The responsible director or building official may permit an applicant to omit required information from an application that the responsible director or building official determines is not material to a decision on the application. An applicant who disagrees with a determination under this subsection may appeal the decision to the city manager.
(C) Except as otherwise provided for in this section, the director is authorized to certify a site plan application if it complies with this subsection.
(1) An application is complete after the applicant pays the required fee and provides the information required to be included in the application no later than the 45th day after the application is submitted.
(2) If the director rejects an application as incomplete, the director shall provide an applicant with a written explanation that identifies the deficiencies and information needed to complete the application. The director must provide the written explanation within 10 working days after the application is received.
(3) An application expires if it is not complete on or before the 45th day after the application is submitted. An applicant may submit additional information and correct any deficiencies at any time before the 45th day after the application was submitted.
(4) A certification that the site plan application is administratively complete is valid for 45 days after the certification has been issued.
(D) The director is authorized to review a site plan application if the applicant pays the required fee and the site plan application has a valid certification of completeness. If the application has not yet been certified, the certification is no longer valid, or the submitted site plan does not match the certified materials, the director may not review the application but shall provide the applicant a written explanation that identifies the deficiencies within 10 working days after application is received.
(E) The responsible director or building official may not accept a building or demolition permit application described in Chapter 25-11, Article 2 (Building and Demolition Permits) unless the application is determined to be complete in accordance with this subsection.
(1) The responsible director or building official shall accept an application as complete if the applicant has paid the required fee and provided the information required to be included in the application no later than the 45th day after the application is submitted.
(2) If the responsible director or building official rejects an application as incomplete, the responsible director or building official shall provide an applicant with a written explanation that identifies the deficiencies and information needed to complete the application. The responsible director or building official must provide the written explanation within 10 working days after the application is received.
(3) An application expires if it is not complete on or before the 45th day after the application is submitted. An applicant may submit an update to provide additional information and to correct deficiencies at any time before the application expires.
(F) An application for a site plan expires one year after the application is submitted unless:
(1) the application has been approved; or
(2) the director has granted additional days for the applicant to submit an update under Section 25-1-90(A) (Extension of Update Deadline).
(G) If the director grants additional days to the applicant under Subsection (F)(2), then the expiration date of the application is extended by the number of days granted.
(H) Applications subject to Section 25-1-712 (Tenant Notification Required).
(1) The responsible director may not certify a site plan application as complete until the applicant has paid the required fee, provided the information required to be included, and complied with the notification requirements or the required number of days lapse.
(2) The responsible director or building official may not accept an application as complete until the applicant has paid the required fee, provided the information required to be included, and complied with the notification requirements or the required number of days lapse.
(3) If, at the time an application is submitted, a multi-family property is unoccupied but was occupied within the previous 120 days, the application will be rejected as incomplete.
(4) If, at the time an application is submitted, a mobile home park is unoccupied but was occupied within the previous 270 days, the application will be rejected as incomplete.
Source: Section 13-1-31; Ord. 990225-70; Ord. 010329-18; Ord. 031211-11; Ord. No. 20140612-084, Pt. 6, 6-23-14; Ord. No. 20160421-039, Pt. 3, 5-2-16; Ord. No. 20160901-050, Pt. 6, 9-12-16; Ord. No. 20190822-117, Pt. 6, 9-1-19; Ord. No. 20230831-141, Pt. 8, 9-11-23; Ord. No. 20230831-103, Pt. 1, 9-11-23.