§ 9-1A-19 — IBC BUILDING CODE AMENDMENT, SECTION 105.3.2, TIME LIMITATION OF APPLICATION
City Code of Boise City, Idaho (2026 S-32: current through Ord. 38-26, passed 9-29-2026) · Boise City Code § 9-1A-19
Corpus is an independent public-information project, not the official City of Boise City website. Stable reference: corpuslaw.us/code/9f4790fa-a7d4-4731-aad6-1fe2e5a73ede
9-1A-19: IBC BUILDING CODE AMENDMENT, SECTION 105.3.2, TIME LIMITATION OF APPLICATION:
105.3.2 Time Limitation of Application. Applications for which no permit is issued within 180 calendar days following the date of receipt of the application shall expire by limitation. Plans and other data submitted for review may thereafter be returned to the applicant or destroyed by the building official or designee. The building official or designee may extend the time for action by the applicant for a period not exceeding 180 calendar days upon request of the applicant demonstrating that circumstances beyond the control of the applicant have prevented action from being taken. No application shall be extended more than three times. In order to renew action on an application after expiration, the applicant shall resubmit application/plans and pay a new plan review fee. In cases where the review was completed, the permit ready but never issued, and expired, an hourly plan review rate in lieu of a new plan review fee may be allowed by the building official under the new application when no changes, or very limited changes to the plans. (Ord. 44-17, 12-19-2017, eff. 1-1-2018; amd. Ord. 39-20, 12-1-2020, eff. 1-1-2021; Ord. 2-25, 2-4-2025)
Ask a question about Boise City law
Corpus searches the Boise City sections it holds and shows the ones that match, with their citations. Free, no sign-in.