Sec. 9.2. - Site plan approval.
9.2.1. Purpose of site plan review. Site plan review shall be required to ensure compliance with land development code and other ordinances as they apply to designated projects, to expedite procedures necessary for obtaining building permits; to provide the developer with one central review of his development proposal; to conserve the time and efforts of city employees in various departments; and to provide for a speedy processing of applications for building permits on large scale and other projects. A Site plan review fee shall be charged in accordance with the adopted fee schedule. 9.2.2. Applicability. Unless determined otherwise by the director of planning, a site plan review shall be required for proposed development including, but not limited to, any subdivision of property, any residential development of five or more dwelling units except individual building lots already approved, any structures with more than two stories, any commercial development adjacent to property zoned for primarily residential use, any development requiring special use or special exception approval, any development located within a flood plain, any commercial development requiring the services of a licensed engineer or architect, any commercial development within 200 feet of a street intersection, any open parking area to be constructed or enlarged, or modifications resulting in the removal and replacement of 50 percent or more of facades of an existing building intended for commercial or mixed-uses. A site plan review by the planning commission shall be required for all development except the following: 9.2.2.1. Any residential development of less than five dwelling units. 9.2.2.2. Any residential, business, or industrial development of one acre or less proposing structures with a cumulative size (within all structures and accessory buildings on the site) of less than 5,000 square feet. Site plans for structures of 5,000 to 10,000 square feet may require approval by the Planning Commission if determined by the Planning Director to be a site of interest to the public. Applications for site plans in this size range will be noticed and posted to allow public input which will inform the Planning Director as to the level of public interest in the site plan. 9.2.2.3. Any parking area of three or less spaces. 9.2.3. Pre-application conference sketch plat. Prior to the submittal of any site plan of an applicant may meet with the planning department to discuss the site plan review process. Applicants are advised to submit a sketch plan for informal advice as to the appropriateness of the proposed site plan. This step does not require a formal application, fee, or filing of plat. A pre-application sketch plan should contain the information and be presented in the form listed in the appendix sketch plan standards. 9.2.4. Procedure. Site plans shall be filed with the director of planning who shall submit the plan to the site plan review committee to determine if all required information has been correctly and sufficiently submitted. No site plan shall be deemed filed and accepted for official review until the director of planning determines that all information required by this section, in appendix A-7, or in any other required ordinance of the City of Oxford has been fully submitted. In all zoning districts other than TND and PUD, a site plan review shall be approvable by the site plan committee (and planning commission when appropriate) as a single review process. For TNDs and PUDs with multiple phases and sub-phases a two-step approval process may be requested allowing approval of a preliminary site plan for each phase independently, and subsequent final site plan approval for sub-phases, following the procedure in section 9.2.10 below. 9.2.5. Compliance. Once the submitted site plan has been accepted for review, the site plan review committee shall complete their evaluation of the site plan and certify to the director of planning that said site plan does or does not comply with all ordinances of Oxford, Mississippi. 9.2.5.1. If the site plan does comply and there is no rezoning or other consideration pending, the director of planning shall approve the site plan or forward the approved site plan to the planning commission for approval (as applicable), and so notify the applicant in writing. 9.2.5.2. If a rezoning application or other consideration is pending, the director of planning shall forward such approved site plan to the planning Commission and the appropriate city departments as applicable along with a written statement that such action is pending, and so notify the applicant in writing. 9.2.5.3. If it is determined that the site plan does not comply, the site plan review committee shall so specify in what respects it does not comply and what additional information is needed to complete the review of the site plan application. This shall be conveyed in writing by the director of planning to the applicant. Correction of all specified items will be required before further processing of the site plan application. 9.2.6. Time period for review. In all cases, the site plan review committee shall have up to or a maximum of 45 calendar days from the date the application is determined to be complete to review and recommend either approval, approval with specific conditions, or disapproval of any site plan. The director of planning may, however, extend the time for the site plan review committee's consideration to allow time for the applicant to submit additional information that is needed to complete the site plan application. If the site plan application requires approval by the planning commission, such extension may require that the application not be heard at the originally scheduled review date before the planning commission. 9.2.7. For an application verified as complete, should the 45-day period expire without action by the committee, the director of planning shall add the application to the agenda of the planning commission for resolution at their next regularly scheduled meeting. 9.2.8. Validity. A site plan approval is valid for 18 months. If permits have not been issued within the timeframe, the site plan is voided unless extended by the planning director. The director may extend the site plan approval for 12-month increments, annually. In considering the extension of any site plan, the director may take into account whether any significant progress has been made toward the completion of all elements of the approved site plan. Any site plan which has not been completed, with occupancy permits issued, within five years shall become subject to any applicable modifications to the land development code. 9.2.9. Site plan amendment procedure. Should the developer of an approved site plan wish to modify any element of the approved site plan; the director of planning shall determine if the modification is significant enough to require approval by the planning commission. Minor waivers, as authorized in this article, may be approved by the director of planning. Appeals of such decisions would be to the planning commission. 9.2.10. Site plan review conditions and approval. 9.2.10.1. The site plan submitted for such development as defined in this section shall provide that the: a. Proposed lot sizes, lot coverage, density, setback provisions, key map showing entire project and its relation to surrounding areas, roads, and water courses, and other factors are in conformity with the requirements of this section and other applicable ordinances and laws. b. It must be determined to have fully complied with the following: Use standards of article 3, mobility and infrastructure standards of article 4, site design and landscaping plan requirements of article 5, tree preservation requirements of article 6, the Signage requirements of Article 7, and the requirements for a certificate of zoning compliance in section 9.8. 9.2.10.2. In addition to such general considerations, said plan shall be approved only after a consideration of the following factors: a. Ingress and egress to the property and any proposed structures with particular reference to vehicular, bicycle and pedestrian safety, traffic flow and control, provision of services and servicing for utilities, and access in case of fire or catastrophe. The routing of vehicle traffic to and through minor residential streets is discouraged. b. Stormwater management plan in accordance with the requirements of chapter 98, article V, Stormwater Management ordinance for the City of Oxford. i. Proposed development should provide for proper surface drainage so that removal of surface waters will not adversely affect neighboring properties or public storm drainage systems and will, so far as practical, conserve the water resources of the area and avoid flooding, erosion, and detrimental depositing of sediments of any kind. No water shall be impounded on roofs, canopies, or paved areas. ii. Surface water shall be disposed of in a manner consistent with sound engineering and ecological practices. iii. The drainage system will be designed so that, except in unusual circumstances, the rate of runoff of surface water from the site in the condition in which it is proposed to be developed will not exceed the rate of runoff from the site in its undeveloped or existing condition. iv. Drainage shall be in compliance with the requirements for stormwater in chapter 98, article V of the City of Oxford Code of Ordinances. c. Conditions on ownership, control and use generally, and conditions on ownership, control, use, and maintenance of open space or common lands to ensure preservation of such lands for their intended purposes. d. All utility connections shall be indicated and shall be in conformity with the standards and requirements for connection to utility companies proposed to serve the property whether said utility companies are public or private. e. Off-street parking and loading areas, with attention to automotive and pedestrian safety, traffic flow and control, access in case of fire and catastrophe, and screening and landscaping. f. Recreation and open spaces, with attention to the location, size, and development of the areas as to adequacy, effect on privacy of adjacent and nearby properties, and relationship to community-wide open spaces and recreation facilities. g. General site arrangement, amenities, and convenience, with particular reference to ensuring that appearance and general layout of the proposed development will be compatible and harmonious with properties in the general area and will not be so at variance with other development in the area as to cause a substantial negative impact on such property values. h. Disposal of waste: Adequate provision for the disposal of all solid, liquid and gaseous wastes and for the avoidance of odor and other air pollutants that may be generated at the site. All applicable pollution control standards shall be observed. i. Noise: All applicable regulations dealing with control of outside noise expected to be generated at the site shall be complied with. j. All setbacks, parking areas, and accessory structures shall be landscaped, located and constructed so as not to interfere with the use of the surrounding property. k. Outside storage areas, service, and machinery installations, service areas, truck loading areas, utility buildings and structures, and similar accessory areas and structures shall be subject to setbacks, screen plantings, or other screening methods as required to prevent adverse effect to the environment or nearby property. l. Traffic impact analysis. At the discretion of the public works department or when any proposed site plan is expected to generate over 100 peak trips, 500 trips in an average day. (See traffic generation threshold table in appendix.) m. Complete street plan. A complete street plan shall be submitted for consideration by public works that includes all existing and proposed infrastructure as it relates to the balancing of bicycle and pedestrian access within the proposed development and the connecting roadways. The plan should address how users on foot or bicycle will navigate into, around, and through the development in compliance with the alternative transportation goals stated in the Vision 2037 Comprehensive Plan. n. For any development proposing common ownership of any elements, common ownership documents, with provision for a property owners' association must be provided before final approval. These must include: 1. Projected date of organization. 2. Organizations structure, included planned timeline for transfer of control from the developer to the association. 3. Diagram of areas to be held in common. 4. Initial estimated fees for the property function of the association. 5. Plan for collective shared maintenance of common areas, including stormwater detention facilities. 9.2.10.3. Site restoration performance bonding. Prior to the issuance of any development permits for all developments requiring site plan approval and exceeding $250,000.00 in estimated construction costs, the developer/owner shall post and maintain a site restoration performance bond or certified check with no less than three years' expiration date to the City of Oxford for an amount not less than 20 percent of the estimated cost of tree mitigation of all significant trees as shown on the tree inventory and 150 percent of the estimated cost to solid sod all disturbed areas as approved by the director of planning and development. a. The site restoration performance bond, or certified check with a notarized statement of intent, shall be provided to guarantee to the city that should the city declare the site or a portion of the site abandoned the site will be restored in accordance with the minimum requirements. If a performance bond is provided, the development and/or the surety company will become obligated to restore the site in accordance with the stated minimum requirements. If a certified check is provided, the notarized statement of intent shall guarantee the right of the city to access the property to restore the site, or have the site restored, in accordance with the minimum requirements. The notarized statement of intent to allow access which shall accompany the certified check shall include the following language: Statement of Intent to Authorize Access to Perform Site Restoration I NAME, developer/owner of and on behalf of NAME OF DEVELOPMENT, approved for SITE PLAN/SUBDIVISION on DATE by the City of Oxford Planning Commission and/or Mayor and Board of Aldermen; agree that if the City of Oxford should declare the site or a portion of the site where NAME OF DEVELOPMENT is abandoned, the City shall have the right to utilize the attached check #NUMBER and to access this property to restore the site, or to have the site restored, in accordance with the minimum requirements as outlined in Sec. 9.2.102. of the City of Oxford Land Development Code. This right shall be extended to any future owner of this development. NAME ADDRESS PHONE b. The minimum work required to restore the site shall be solid sodding of all disturbed areas and trees planted in accordance with the tree mitigation requirements as required by the landscape ordinance and approved by the director of planning, but not to exceed the amount of the site restoration bond, certified check, or letter of credit. c. Factors that are evidence of site abandonment, or portions of a site abandonment, include but are not limited to the following. All factors do not have to be present for the city to declare the site or a portion of the site abandoned; however, subsections i. and ii. must apply: i. Eighteen months have elapsed since final site plan, development plan or subdivision plat approval with no building permits issued; ii. Six months have elapsed since issuance of a building permit without construction activity underway on the site; iii. No documented substantial work is being performed on the site and/or structures based on three separate visual site inspections by city staff occurring weekly for three consecutive weeks; iv. Within 45 days for a single-family structure and within six months for all other structures from the issuance of a building permit and the foundation and slab are not completed; v. Within six months for a single-family residential structure and within 12 months for all other structures after the issuance of a building permit and the framing, electrical, and plumbing are not completed; vi. Within 12 months for a single-family residential structure and within 18 months for all other structures after the issuance of a building permit and the certificate of occupancy has not been issued; vii. Abandonment. After a determination has been made by the planning director that a site has been abandoned, a certified letter will be sent by the city to the developer/owner/surety company notifying them that they have the opportunity to request, within 30 days from the date of the certified letter, one six-month extension from the planning director before the city initiates site restoration activities by contacting the surety company. The director of planning will consider the factors listed above when considering if a six-month extension is warranted and the extension is solely at the discretion of the building official. d. Site restoration activities may also include, at the discretion of the director of planning debris removal, seeding, sodding, tree and vegetation installation, correction of public safety hazards (including but not limited to structures open to the elements, incomplete infrastructure improvements that pose a public safety hazard, and incomplete streets that cannot accommodate public safety vehicles), and as much as possible, re-establishment of the site's original topography. The site restoration performance bond, certified check, or letter of credit shall be in effect until a certificate of occupancy is issued by the City of Oxford. The developer/owner shall notify the director of planning and development in writing within 15 days of any proposed changes in the status of the bond, certified check, or letter of credit. The director of planning and development must approve any changes of the bond, certified check, or letter of credit. 9.2.11. Procedure for preliminary and final site plans for TND and PUD districts. 9.2.11.1. Compliance. Once the submitted preliminary or final site plan has been accepted for review, (as outlined in section 9.2.3) the site plan review committee shall complete their evaluation of the site plan and certify to the director of planning that said site plan does or does not comply with all applicable ordinances of Oxford, Mississippi. a. If the preliminary or final site plan does comply and there is no rezoning or other consideration pending, the director of planning shall approve the site plan or forward the approved site plan to the planning commission for approval and so notify the applicant in writing. b. If a rezoning application or other consideration is pending, the director of planning shall forward such approved preliminary or final site plan to the planning commission and the appropriate city departments along with a written statement that such action is pending, and so notify the applicant in writing. c. If it is determined that the preliminary or final site plan does not comply, the site plan review committee shall so specify in what respects it does not comply and what additional information is needed to complete the review of the site plan application. The director of planning shall give this information to the applicant in written form; and all specified items must be corrected before further processing of the site plan application. 9.2.11.2. Time period for review. In all cases, the site plan review committee shall have up to or a maximum of 45 days from the date of filing to review and recommend either approval, approval with specific conditions, or disapproval of the preliminary or final site plan being evaluated. The director of planning may, however, extend the time for the site plan review committee's consideration to allow time for the applicant to submit additional information that is needed to complete the site plan application. If the preliminary or final site plan application requires approval by the planning commission, such extension may require that the application not be heard at the originally scheduled review date before the planning commission. 9.2.11.3. Action of the committee binding. Subject to approval by the planning commission and the mayor and board of aldermen (if required), action of the site plan review committee shall be binding on all city departments as far as final site plan approval for obtaining a building permit is concerned. For an application verified as complete, should the 45-day period expire without action by the committee, the director of planning shall immediately forward the application to the planning commission for resolution at their next regularly scheduled meeting. 9.2.11.4. Validity. A preliminary site plan approval shall be valid for 12 months before a final site plan must be submitted for review for the established sub-phases of the development. A final site plan approval shall be valid for 18 months before permits must be issued to the developer. If permits are not issued as required, the site plan is then voided subject to the annual review of the director of planning. 9.2.11.5. Site plan amendment procedure. Should a developer with an approved preliminary or final site plan wish to modify any element of the approved site plan; the director of planning shall determine if the modification is significant enough to require approval by the planning commission. Minor waivers, as authorized in this article, may be approved by the director of planning in consultation with applicable members of the site plan committee. Appeals of such decisions shall be to the planning commission. 9.2.11.6. Preliminary site plan review factors for approval. Site plans shall provide sufficient information to ensure: a. That the proposed lot sizes, lot coverage, density, setback provisions, and (on the map showing the entire project and its relation to surrounding areas) that roads, and water courses, and other factors are in conformity with the requirements of this section and other applicable ordinances and laws; and b. That the preliminary site plan substantially complies with the following: Use standards of article 3, mobility and infrastructure standards of article 4, site design and landscaping plan requirements of article 5, tree preservation requirements of article 6, and the signage requirements of article 7. c. That proposed ingress and egress to the property and any proposed structures with particular reference to vehicular bicycle, and pedestrian safety, traffic flow and control, provision of services and servicing for utilities, and access in case of fire or catastrophe meet city standards. The routing of substantial vehicle traffic through minor residential streets is discouraged. d. Stormwater management plan in accordance with the requirements of chapter 98, article V, stormwater management ordinance for the City of Oxford. i. Proposed development should provide for proper surface drainage so that removal of surface waters will not adversely affect neighboring properties or public storm drainage systems and will, so far as practical, conserve the water resources of the area and avoid flooding, erosion, and detrimental depositing of sediments of any kind. No water shall be impounded on roofs, canopies, or paved areas. ii. Surface water shall be disposed of in a manner consistent with sound engineering and ecological practices. iii. The drainage system will be designed so that, except in unusual circumstances, the rate of runoff of surface water from the site in the condition in which it is proposed to be developed will not exceed the rate of runoff from the site in its undeveloped or existing condition. iv. Drainage shall be in compliance with the requirements for stormwater per chapter 98, article V of the City of Oxford Code of Ordinances. e. That all proposed utility connections shall be indicated and shall be in conformity with the standards and requirements for connection to utility companies proposed to serve the property whether said utility companies are public or private. f. That the preliminary proposals for off-street parking and loading areas reflect attention to automotive and pedestrian safety, traffic flow and control, access in case of fire and catastrophe, and initial concepts for required screening and landscaping. g. That the preliminary proposals for recreation and open spaces, reflect attention to the impact of the proposed location, size, and development of the areas as to adequacy, effect on privacy of adjacent and nearby properties, and relationship to community-wide open spaces and recreation facilities. h. That the proposed density, design, and/or purpose of the development reflect attention to its relationship to adjacent and nearby properties; and result in minimal degradation of unique or irreplaceable land types. i. That adequate provision is made for the disposal of all solid, liquid and gaseous wastes and for the avoidance of odor and other air pollutants that may be generated at the site. All applicable pollution control standards shall be observed. j. That all setbacks, parking areas, and proposed accessory structures are located where they do not interfere with the use of the surrounding property. k. That all infrastructure has been planned and provided for to address how users entering on foot or bicycle will navigate into, around, and through the development in compliance with the alternative transportation goals in the Vision 2037 Comprehensive Plan. 9.2.11.7. Final site plan review factors for approval. Site plans shall provide sufficient information to determine: a. That the final site plan has fully complied with the following: Use standards of article 3, mobility and infrastructure standards of article 4, site design and landscaping plan requirements of article 5, Tree preservation requirements of article 6, and the signage requirements of article 7. b. That all required conditions on ownership; control and use generally; and conditions on ownership, control, use, and maintenance of open space or common lands to ensure preservation of such lands for their intended purposes have been submitted and approved. c. That all off-street parking and loading areas meet all screening and landscaping reqirements. d. That all proposed recreation and open spaces; considering their location, size, and facilities; adequately provide privacy for adjacent and nearby properties, and have a relationship to any community-wide open spaces and recreation facilities. e. That the proposed site plan reflects compliance with all applicable regulations dealing with control of outside noise expected to be generated at the site. f. That all setbacks, parking areas, and accessory structures meet the landscaping and screening requirements of this ordinance. g. That all proposed outside storage areas, service, and machinery installations, service areas, truck loading areas, utility buildings and structures, and similar accessory areas and structures meet all requirements for setbacks, screen plantings, or other screening methods as required to prevent adverse effect to the environment or nearby property, as required in this ordinance. h. That all infrastructure has been planned and provided to address how users on foot or bicycle will navigate into, around, and through the development in compliance with the alternative transportation goals stated in the Vision 2037 Comprehensive Plan. 9.2.12. Construction staging plan. As the city desires all construction projects to minimize the impact on neighboring properties and the general public a construction staging plan will be required for all commercial building projects, large subdivisions, master planned developments, multi-family projects and other projects as required by the site plan review committee. A construction staging plan shall include: 9.2.12.1. Information required. A construction staging plan shall include: a. Information regarding the site layout of temporary construction measures that will be used to protect the general public in the vicinity of the work site. b. Where materials are to be staged on or off the site. c. The timeline of the construction project. d. Plans to ensure that access to any meter or equipment used by the city for utility service shall not be blocked. e. Walkways: Shall be provided in accordance with current building code adopted by the City of Oxford. f. Directional barricades: Shall be provided in accordance with current building code adopted by the City of Oxford. Jersey barricade or similar protections shall be installed as directed by the city engineer. g. Barriers: Provide in accordance with current building code adopted by the City of Oxford and as follows. h. Openings in barriers shall be protected by lockable doors with key(s) placed into the Knox box (see below). Indicate the location of all doors. Doors shall be locked at all times construction workmen are not on the site. i. Covered walkways: Shall be provided in accordance with current building code adopted by the City of Oxford. Covered walkways shall be installed where walkways open to pedestrian traffic are located within 15 feet horizontally of any construction work occurring higher than 15 feet above grade. j. Temporary construction fence: Temporary construction fence may be installed in lieu of a barrier along portions of the perimeter of a construction site as follows: i. The fence shall be a minimum eight feet high chain link fence with opaque fabric installed full height on the inside surface to reduce view into the site and control dust. ii. The fence shall be secured with posts driven into the ground at eight feet on center maximum spacing to maintain the fence in a plumb condition at all times. iii. Openings in fence shall be protected by lockable gates with key(s) placed into the Knox box (see below). Indicate location of all gates. Gates shall be locked at all times construction workmen are not on the site. k. Protection of adjoining property. i. Provide protection in accordance with IBC 3307.1. ii. All physical means of protection shall be indicated on the construction staging plan. iii. A construction staging plan shall indicate directional routes for constructions vehicles away from adjoining residential streets to the greatest possible extent. iv. Litter and construction debris shall be disposed of daily. l. Construction sign: Indicate the location of the sign which shall be secured to a barrier or temporary construction fence. The sign shall display the following verbiage: i. "CONSTRUCTION SITE-NO TRESPASSING." ii. The contractor's name and 24-hour emergency contact telephone number. iii. The barrier and/or fence contractor's name and 24-hour emergency contact telephone number. iv. Knox box: Indicate location of a Knox box containing keys to allow the fire department ready access to the construction site and locked structures thereon. The Knox box style and mounting location shall be approved by the fire department. v. Pedestrian traffic control devices: Indicate location and verbiage for sidewalk closure signage, i.e. "SIDEWALK CLOSED AHEAD-USE SIDEWALK ACROSS STREET," etc. vi. Vehicular traffic control devices: Indicate location of Jersey Barriers or other devices to be used for sectioning off roadways for material movement activities or placement of crane. Jersey barriers shall be fitted with flashing lights at each end and at 50 foot intervals in between. m. Traffic: Directional routes for constructions vehicles shall be established that direct construction traffic away from adjoining residential streets to the greatest possible extent. n. Dumpster: Indicate size and location of the dumpster to be used for construction debris. o. Construction staging area: Indicate location of construction staging areas, including the location of construction hoists, cranes, delivery areas and fabrication areas. p. Material storage: Indicate location of the area to be used for storage of construction materials to be incorporated into the work. q. Fire Extinguishers: Provide in accordance with current building code adopted by the City of Oxford and as directed by the fire department. r. Porta-potty: Indicate the location of portable or temporary toilet facilities. s. Traffic plan: Provide drawing or written narrative indicating proposed street paths to be used for movement of equipment and debris. t. Parking plan: Provide drawing or written narrative indicating proposed parking areas to be used for parking for construction workers. Parking permits may be required. u. Temporary water: Indicate location of temporary water source or public hydrant to be used for construction water. A hydrant meter deposit is required for the use of all city hydrants for construction purposes. v. Operation of sidewalks and bicycle lanes. Provide a narrative detailing how existing sidewalks and bicycle lanes will be kept free of signs, debris, or other obstructions in order to remain open and accessible at all times. If there are known times that the sidewalk or bicycle lane must be blocked, provide detailed explanation of the reason, time period, and alternate route to be made available to the public to the City Engineer for approval. Narrative should also include the name and contact information for the person responsible for daily checks of all sidewalks and bicycle lanes for compliance with the construction staging plan. 9.2.12.2. Modification to a construction staging plan. Modification to the staging plan will not require a formal amendment to site plan provide the modification is approved by the director of planning, chief of police, chief of the fire department, director of planning, and director of public works or their designated representative. 9.2.13. Decisions of the planning commission. Whenever application for a site plan approval has been denied by the planning commission, then the planning commission shall not consider any further petition requesting the same or substantially the same change or amendment for the same property within six months from the date of the planning commission's final legal action on that petition or from the date of the planning commission's decision of that petition. For the purpose of this section, any petition withdrawn prior to a decision by the planning commission may be resubmitted without regard to the six-month limitation.
(Ord. No. 2018-11, 7-17-2018; Ord. No. 2018-21, § V, 10-16-2018; Ord. No. 2025-2, § I, 1-21-2025; Ord. No. 2025-19, § 1, 12-2-2025)
Ask a question about Oxford law
Corpus searches the Oxford sections it holds and shows the ones that match, with their citations. Free, no sign-in.