§ 14-11-132 - APPLICATION REQUIRED.
(A) Except as provided in Subsection (B), to obtain a temporary use of right-of-way permit or a renewal or extension of a temporary use of right-of-way permit, a person must make written application to the director on a prescribed form not later than the ninth day before the person intends to use the right-of-way.
(B) The director may accept an application after the deadline established in Subsection (A) for good cause as determined by the director.
(C) In an application, an applicant must:
(1) state the reason that use of the public right-of-way is necessary; and
(2) demonstrate that the applicant's proposed use of the right-of-way is the minimum necessary to perform the proposed activity.
(D) In an application, an applicant must agree to:
(1) comply with permit conditions; and
(2) accept service of a written notice of violation presented to the applicant, site manager, site supervisor, project superintendent, or prime contractor by a city official.
(E) An applicant must attach proof of compliance with Sections 14-11-102 (Insurance Required) and 14-11-103 (Security Required).
(F) If a temporary use of right-of-way permit is necessary to perform work under a building permit, demolition permit, driveway approach permit, or other City permit, an application for the temporary use of right-of-way permit must accompany an application for the building, demolition, driveway approach, or other City permit.
(G) An application submitted under Subsection (A) must be accompanied by a nonrefundable application fee established by separate ordinance.
Source: Ord. No. 20170817-045, Pt. 2, 8-17-17; Ord. No. 20220505-030, Pt. 3, 5-16-22.