Approval by failure of planning commission to act in time--Exception if longer period granted.
SDCL § 11-2-24.1
in effect11-2-24.1. Approval by failure of planning commission to act in time--Exception if longer period granted.
The failure of the planning commission to act within sixty-five days from and after the date of official submission to it under the provisions of § 11-2-24, shall be deemed approval, unless a longer period be granted by the board or other submitting official.
SL 1975, ch 113, § 14.
Source: South Dakota Legislature (sdlegislature.gov)URL: https://sdlegislature.gov/Statutes/11-2-24.1Fetched: 10/20/2026