Deposit of certain retained funds on certain construction contracts; penalty for failure to timely complete.
Norfolk City Code § 33.1-56
in effectSec. 33.1-56. - Deposit of certain retained funds on certain construction contracts; penalty for failure to timely complete.
(a) Contracts of two hundred thousand dollars ($200,000.00) or more for construction of highways, roads, streets, bridges, parking lots, demolition, clearing, grading, excavating, paving, pile driving, miscellaneous drainage structures, and the installation of water, gas, sewer lines and pumping stations in which portions of the contract price are to be retained, shall include in the invitation to bid an option for the contractor to use an escrow account procedure for utilization of the retainage funds by so indicating in the space provided in the bid documents. In the event the contractor elects to use the escrow account procedure, the "escrow agreement" form included in the invitation to bid and contract shall be executed and submitted to the political subdivision within fifteen calendar days after notification. If the "escrow agreement" form is not submitted within the fifteen-day period, the contractor shall forfeit his rights to the use of the escrow account procedure.
(b) In order to have retained funds paid to an escrow agent, the contractor, the escrow agent, and the surety shall execute an "escrow agreement" form. The contractor's escrow agent shall be a trust company, bank or savings institution with its principal office located in the commonwealth. The "escrow agreement" and all regulations shall be substantially the same as that used by the Commonwealth of Virginia Department of Transportation.
(c) This section shall not apply to public contracts for construction for railroads, public transit systems, runways, dams, foundations, installation or maintenance of power systems for the generation and primary and secondary distribution of electric current ahead of the customer's meter, the installation or maintenance of telephone, telegraph or signal systems for public utilities and the construction or maintenance of solid waste or recycling facilities and treatment plants.
(d) Any such public contract for construction which includes payment of interest on retained funds may require a provision whereby the contractor, exclusive of reasonable circumstances beyond the control of the contractor stated in the contract, shall pay a specified penalty for each day exceeding the completion date stated in the contract.
(e) Any subcontract for such public project which provides for similar progress payments shall be subject to the provisions of this section.
(Ord. No. 35,589, § 1, 6-20-89)