§ 26-190 — Compliance with plan
Code of Ordinances, City of Tupelo, Mississippi (Supp. No. 15: codified through Ordinance of March 5, 2024 and Ordinance of June 4, 2024) · Tupelo Code of Ordinances § 26-190
Corpus is an independent public-information project, not the official City of Tupelo website. Stable reference: corpuslaw.us/code/053f217f-80f4-42e2-b534-bc6021c1e2ae
Sec. 26-190. - Compliance with plan.
(a) If any or all of the criteria in this article cannot be met, the administrator may reject the site plan. The rejection of the stormwater retention and detention site plan shall prevent the granting of any building permit for the development until such time that an acceptable stormwater retention and detention site plan is approved by the administrator. In making the decision to reject the site plan, the administrator shall consider the following factors: (1) The degree of compliance with the criteria set forth in section 26-189; (2) The detrimental impact on surrounding property and existing drainage systems and facilities caused by a failure to comply; (3) The cost to the developer of a required stormwater retention and detention plan which would comply. (b) The administrator is empowered and directed to make inspections of each development once the site plan is approved and a building permit issued. Failure to comply with the specifications of the approved site plan will result in a revocation of the building permit.
(Ord. of 12-19-89, § 4(4.3))
Ask a question about Tupelo law
Corpus searches the Tupelo sections it holds and shows the ones that match, with their citations. Free, no sign-in.
