May permanent improvements be made under a WSR lease?
25 C.F.R. § 162.543
in effectEffective (a) A WSR lease must provide for the installation of a facility and associated infrastructure of a size and magnitude necessary for the generation and delivery of electricity, in accordance with § 162.019. These facilities and associated infrastructure are considered permanent improvements. A resource development plan must be submitted for approval with the lease under § 162.563(h).
(b) If the parties agree to any of the following changes to the resource development plan after lease approval, they must submit the revised plan to BIA for the file:
(1) Location of permanent improvements;
(2) Type of permanent improvements; or
(3) Delay of 90 days or more in any phase of development.