in effectSec. 5-5-17. - Review of actions of plumbing inspector.
When the plumbing inspector disapproves all or part of the fixture work in any building, the owner may, within five days after receiving the written notice from the plumbing inspector, file a petition in writing for review of such action of the plumbing inspector to the chairman of the board of examiners of plumbing. Upon receipt of such petition the board shall proceed to determine whether such plumbing construction complies with this article, and within three days the board shall make a decision in accordance with its findings.
(Ord. No. 2199, § 2, 3-6-12)