Sec. 158-58. - Integrated resource plan.
The integrated resource plan ("IRP") is a triennial process that assesses the energy resources available to meet the electric service needs of the City of New Orleans and ensures that changes in customer demands and environmental conditions are addressed effectively and presented in a final IRP report filed by the utility. The goal of the IRP is to identify the optimal set of resources to meet the current and future electric service needs of the city, at the lowest total cost to customers and utility, in a manner consistent with the public interest and the council's energy policy goals. The expected combination of costs, reliability, risks, and uncertainty are all considered in this process.
(a) Procedural overview. The minimum procedural schedule requirements for an IRP shall be as follows:
(1) Initiating resolution. The council adopts an initiating resolution outlining the IRP process, intervenor and public participation, policy objectives, procedural schedule, and any other matters deemed necessary by the council. The IRP process shall include an opportunity for intervenors to participate in the concurrent development of inputs and assumptions for the major components of the IRP in collaboration with the utility within the confines of the IRP timeline and procedural schedule.
(2) Public meetings. CURO shall schedule at least three public engagement meetings. The meetings will be advertised at least 30 days prior to the public technical conferences. A description of the meetings to be scheduled are as follows:
A. Public meeting 1: An initial meeting that describes the IRP process including the purpose of the IRP and procedural timelines.
B. Public meeting 2: The utility presents its IRP as filed.
C. Public meeting 3: Dedicated to public comment on the utility's IRP report.
(3) Technical meetings. CURO shall schedule at least four technical meetings in which parties will be able to discuss the major IRP components, including present inputs and assumptions, provide comments, and attempt to reach consensus.
(4) Additional information related to this division is contained in the IRP rules section of the URM.
(b) Policy objectives for IRP consideration. In addition to the analysis components described above, the IRP incorporates policy objectives as determined by the council including, but not limited to:
(1) The renewable and clean portfolio standard ("RCPS") program. To pursue reductions to carbon emissions, improve the health and quality of life of the citizens of New Orleans, and to reduce the city's impact on climate change, compliance with the council's RCPS should be incorporated into the planning strategy reflecting known utility regulatory policy goals of the council.
(2) Energy Smart Program kW and kWh reduction goals. Upon the conclusion of the utility's IRP report filing, the utility should include, for evaluation by CURO, council advisors, and intervenors, Energy Smart Program goals of increasing the projected annual kWh savings at a rate equal to a percentage of kWh sales and reducing the utility system peak load.
(3) Transmission and distribution planning. Transmission and distribution planning should be more fully integrated into the IRP process to ensure that transmission and distribution solutions are considered as alternatives to supply-side and demand-side resources are evaluated, and that any reliability concerns and customer-owned distributed energy resources are addressed.
(4) Optimization software. To ensure that demand-side resources are compared equally with supply-side resources in all IRPs, all supply-side and demand-side resource alternatives should be made available to the utility's select optimization engine concurrently such that the optimization software can choose an optimal combination of resources.