Sec. 10-296. - Specific water service areas and area-specific water main extension fees.
(a) At the time of application for a permit to construct and extend a water main, the applicant may request that the town approve construction whereby the applicant agrees to construct a water main with a capacity in excess of the size required to serve his development.
(b) If the town engineer finds that such construction is in accordance with any water service plan of the town, that the construction is in the public interest and that the water main extension would have sufficient capacity to serve property not owned by the applicant, the town engineer may recommend to the council the adoption of a specific water service area and the establishment of an area-specific water extension fee.
(c) The council may, by ordinance, establish a specific water service area and an area-specific water main extension fee. The ordinance shall contain the following:
(1) A description or map showing the specific water service area.
(2) The cost of construction and installation of the water main and related facilities or a method to determine same.
(3) A requirement that all landowners or other persons who connect to the water main extension shall pay to the town an amount equal to his pro rata share, based on front footage, of the cost of construction and installation of a water main extension and administration costs of the town incurred in administering the specific water service area.
(d) Prior to connection of a water line to the water main extension and the specific water service area, the town may require such person to pay to the town his pro rata share of the costs, as set forth in subsection (c)(3) of this section.
(e) The town shall refund to the applicant the cost of installation of the water line extension; provided however, that all administrative costs incurred by the town shall first be deducted and provided further that in no case will the refunded amount exceed the total funds to be collected by applicant.
(f) Upon the recommendation of the director of public works, the town may advance the costs of construction of a water main extension with a capacity to serve a specific waste service area, and may establish an area-specific water main extension fee pursuant to subsection (c) of this section. The area-specific water main extension fee shall be utilized to reimburse the town for the cost of construction of the water main extension and related facilities.
(Code 1984, § 9-2-5)