27.30.030 - Change order.
"Change Order" means a written amendment to the Public Works Contract or work order, executed by both the City and Contractor, that does any of the following:
A. Changes the scope of work in the contract;
B. Adjusts the time for completing all or a portion of the scope of work in the contract;
C. Adjusts the Contractor's compensation to reflect any change in the scope of work or any time adjustment; or
D. Makes any other changes arising from a change to the scope of work, a time adjustment or an adjustment to the Contractor's compensation.
(Ord. 30308.)