Change in contractor—Reissuance of permit—Fees.
Metropolitan Code of Nashville and Davidson County § 16.28.260
in effect16.28.260 - Change in contractor—Reissuance of permit—Fees.
When a change in a contractor occurs before a job is completed, the contractor who obtains the permits shall notify the codes department in writing. A new permit shall be taken out for the unfinished construction. The contractor that completes the construction shall pay a prorata permit fee based upon the unfinished construction; but in no case, less than the minimum permit fee.
(Ord. 98-1445 § 81, 1998)
Source: Metropolitan Government of Nashville and Davidson County, Metropolitan Code and Charter (Municode Library, library.municode.com)URL: https://library.municode.com/tn/metro_government_of_nashville_and_davidson_county/codes/code_of_ordinances?nodeId=CD_TIT16BUCO_CH16.28BUPE_16.28.260CHCOEIPEEEFetched: 10/28/2026