Application for use of utility infrastructure.
Round Rock Code of Ordinances § 44-310
in effectSec. 44-310. - Application for use of utility infrastructure.
(a) Authorized users. Unless otherwise required by law, only applicants who hold a valid franchise or license to use or utility infrastructure, granted by the city, will be granted attachment rights on utility infrastructure. The applicant shall be authorized to use utility infrastructure only for the purposes specified in its franchise or license. Attachments that are used for a purpose other than that authorized in the applicant's franchise or license shall be deemed to be unauthorized attachments. Persons who seek to use utility infrastructure for private purposes may not be granted attachment rights hereunder.
(b) Application process. To obtain the right to use utility infrastructure, an applicant must file an application with the PWD in accordance with procedures developed by the PWD. Subject to availability of utility infrastructure capacity, all applications shall be considered on a first come, first serve basis. If an application cannot be approved as presented, PWD may approve an application subject to conditions. All conditions of approval shall be incorporated into the infrastructure usage license agreement.
(c) Denial of an application.
(1) An application may be denied if:
a. The applicant fails to submit a complete application;
b. The applicant fails to supplement its application with additional information or otherwise cooperate with the city as requested in the evaluation of the application;
c. The applicant fails to timely pay the required filing fees;
d. The proposed attachments are of excessive size or weight or would otherwise subject utility infrastructure to unacceptable levels of additional stress;
e. Approval would jeopardize the reliability or integrity of the public utility systems or of individual units of utility infrastructure;
f. Approval would present a safety hazard to city employees or the public;
g. Approval would impair the city's ability to operate or maintain utility infrastructure;
h. Approval would require an unacceptable change, upgrade or addition to utility infrastructure; or,
i. Approval would expose the city, the PWD, the public, or other users to increased liability or financial risk.
(2) If an application is denied, the applicant shall be given written notice of the basis for denial. The denial of an application shall be without prejudice to the right of applicant to file a new application correcting any deficiencies that led to denial. If an application is denied, applicant shall have the right to appeal the denial of its application to the director of the PWD or designee no later than 30 days after the date of the action being appealed, in accordance with procedures to be developed by the PWD. If, on appeal, the director of the PWD or designee upholds the original PWD decision, such that the applicant has been denied all, or substantially, all attachment rights, the applicant may appeal to the city council in accordance with section 44-313.
(3) Additional costs. All costs to replace, enlarge or upgrade utility infrastructure to accommodate the proposed attachments of an applicant or user, as determined by the PWD, shall be borne by the applicant or user.
(4) Infrastructure usage agreement.
a. The city attorney, in conjunction with the PWD, shall develop an infrastructure usage license agreement consistent with this chapter.
b. The infrastructure usage license agreement must be fully executed and approved before the applicant may undertake any work or make any attachments on any utility infrastructure.
c. The applicant must pay all usage charges for the initial contract year in advance at the time of execution of the contract.
d. If the annual usage charges to be paid to the city under an infrastructure usage license agreement are less than the amount specified in the city Charter as requiring approval of contracts by the city council, the director of the PWD, or designee, is hereby authorized to enter into and execute such infrastructure usage contract on behalf of the city without further action by the city council. Infrastructure usage license agreements which will generate annual usage charges greater than said amount specified in the city Charter or in this Code shall be subject to approval by the city council.
e. The license agreement shall identify and establish procedures to limit the number, kind and location of attachments that the user may place on any utility infrastructure, the method of construction or installation of user's attachments, and the authorized use of the attachments by user. User may not change the number, kind, location of attachments, the method of construction or installation, or the use of the attachments authorized under such contract without the prior written consent of the PWD, which shall not be unreasonably withheld. The denial or approval of an individual permit or attachment shall be governed exclusively by the terms of the infrastructure usage contract, and shall not be subject to the provisions of section 44-313.
(Code 1995, § 10.1005)
Source: City of Round Rock, Texas, Code of Ordinances (Municode Library, library.municode.com)URL: https://library.municode.com/tx/round_rock/codes/code_of_ordinances?nodeId=PTIICOOR_CH44UT_ARTXUSTHPACINEUTIN_S44-310APUSUTINFetched: 11/16/2026