Sec. 22-2. - Temporary certificate of occupancy (TCO) issuance and fee schedule.

(a) Issuance. The building official/senior building inspector is authorized to issue a temporary certificate of occupancy prior to the completion of the work covered by the permit and/or required by other provisions of the municipal codes of the City of Oxford, provided that such portion or portions may be occupied safely. Temporary certificates of occupancy may be issued in increments of 30 days for a maximum cumulative period of 180 days. (b) Revocation. The building official/senior building inspector is authorized to, in writing, suspend or revoke a temporary certificate of occupancy wherever the certificate is issued in error, or on the basis of incorrect information supplied, or where it is determined that the structure or any portion thereof is in violation of any ordinance or regulation, or where an unsafe condition is found as determined by the building official/senior building inspector or personnel with the oxford fire department inspection division. (c) Fee schedule. Fifteen percent of the permit cost with a $300.00 minimum for the first 30-day period or fraction thereof. Twenty-five percent of the permit cost with a $600.00 minimum for the second 30-day period or fraction thereof. Thirty-five percent of the permit cost with a $1,000.00 minimum for each 30-day period or fraction thereof after the second. If landscaping requirements are the only prohibitions to the issuance of the permanent certificate of occupancy, a one-time fee of ten percent of the cost of the permit with a $300.00 minimum and a $1,000.00 maximum will be assessed. The temporary certificate of occupancy issued for only landscaping shall be issued for a time period not to exceed 180 days. If all landscaping requirements are not met within the allotted 180-day period, the city may utilize the certificate of deposit or letter of credit furnished in accordance with section 5.7.2.4 of the land development code to install or complete the installation of the required landscaping.

(Ord. No. 2025-4, § I, 6-3-2025)