Tyler City Code § 6-100 Bond and general requirements for demolition permits.
Sec. 6-100. Bond and general requirements for demolition permits.
a. A demolition permit may not be issued unless the applicant provides a cash bond or a performance bond payable to City according to the following schedule:
Floor Space Bond
Residential Structures
500 square feet or less $ 100.00
501750 square feet 150.00
7511000 square feet 200.00
1001 square feet or more 300.00
Commercial Structures
01,200 square feet $1,000.00
Over 1,200 square feet 2,000.00
b. The owner of real property upon which a structure is situated is exempt from the bonding requirements of this section if the owner personally applies for a permit, certifies that owner has not contracted for the demolition work and that all such work will be performed by owner or employees or agents under owner’s direct supervision.
c. A contractor under a contract for demolition with the City is exempt from the bonding requirements of this section as to all structures covered under the contract.
d. A demolition permit shall specify a reasonable time period in which the building or structure shall be demolished. The time limit specified shall be the minimum time necessary to demolish the structure and to remove trash and debris from the site as required by this section. The permit shall further specify what portion(s) of the structure may be left intact. The Chief Building Official shall not allow any portion of the structure to remain intact if the remaining portion of the structure would (1) present a safety hazard or (2) would be unsightly. This section shall not apply if (1) the applicant has been granted a permit to rebuild a structure over the remaining portion of the original structure, and (2) the permit holder timely proceeds to construct the new structure in accordance with the permit.
e. By the expiration date of the permit, the permit holder shall leave the demolition site free of all trash, debris, and salvage.
f. The performance bond or cash bond shall be conditioned upon performance by the permittee in (1) timely demolishing the structure and removing all portions except the portions that may remain intact in accordance with the permit and (2) removing all debris from the site prior to the expiration date of the permit.
g. The Chief Building Official for cause, may extend the time limit of the permit for up to thirty (30) days.
h. If the permittee fails to demolish the structure and remove all debris as may be required under the permit and this section, the City may apply all or any part of the proceeds from the performance bond or the cash deposited in lieu of the performance bond to defray the cost of completing the demolition and removing the debris from the site.(Ord. No. 0-97-29, 6/18/97)