Permit application.
Hattiesburg Code of Ordinances § 46-101
in effectSec. 46-101. - Permit application.
(a) No permit shall be issued without a completed application and the approval by the city engineer or his/her permit administrator. The application shall be completed and submitted to the building division of the city's department of urban development and shall minimally include drawings with a detailed description of the size, type, nature, and extent of the work or construction to be done; the exact location and approximate area where the anticipated work or construction is expected to occur, including the approximate length and width and, if the excavation or digging is in a street or alley, whether it is parallel or transverse to the direction of the travel lanes; and the distance between any existing entrances within 100 feet of the proposed work or construction; distance from the centerline of the traveled way to any structures, gasoline pumps, or other obstructions within 100 feet of the proposed work or construction; property lines and easements within 100 feet of the proposed work or construction; the length, size and location of existing pipes, culverts, catch basins or manholes, conduit, curbing, curb and gutter, and/or sidewalks, and aboveground utilities within 100 feet of the proposed work or construction; and the proposed location of new pipes, conduit, any existing utilities, culverts, catch basins or manholes, curbing, work or construction sought to be completed. All drawings must be to scale.
(b) First time applicants must submit a contractor worksheet. This allows the engineering department to review contractors to ensure they are qualified to do the required work. In order to be able to work in the city, contractors must be licensed and bonded with the city and state. Contractors are also required to show and state previous work history with valid references.
(c) Any construction or disturbance on city right-of-way must be permitted through the engineering department. Notwithstanding the above provision, regular maintenance to utility lines, conduits, manholes, power poles, etc., that does not disturb the public ROW is excluded. Maintenance work that does cause disturbance to the public ROW must first be permitted consistent with the following requirements. If the maintenance is disturbing less than 100 square feet, said job can be permitted through a maintenance permit that will include company, representative, contractor, maintenance reasoning, and simple drawing detailing the size, type, nature, and extent of the work to be done. Maintenance permits will be approved or denied within two working days of submittal.
(d) Except for requirements subject to the exclusive jurisdiction of another regulatory agency or governing state or federal body or any valid agreement or franchise, the location, depth and other physical characteristics of any facilities or construction for which a permit is issued hereunder shall be subject to approval of the city engineer or his/her designee, such approval not to be unreasonably withheld and to be based on, but not limited to, maintenance, operation, and oversight of the affected streets, alleys, sidewalks, rights-of-way and construction areas.
(e) Permittees are required to submit a contractor worksheet along with the first application submittal. Once the city engineer approves said contractors, they may be used on each application submittal. If the applicant wishes to use a new contractor, he/she is required to submit a new contractor worksheet to be approved or denied by the city engineer.
(Ord. No. 3236, § 2, 7-17-2018)