14.04.040 - Mains and main extensions.
A. Unless otherwise approved by the director, all service connections shall be made to a wastewater main that is located immediately adjacent to the property requiring service. The director reserves the right to determine the wastewater main to which connection shall be made.
B. Applicants requesting service to a property where no city wastewater main exists contiguous to the property must first arrange for a wastewater main extension in accordance with this title and department service rules. Where such wastewater main exists but does not extend across the full extent of the property frontage or is within 400 feet of the property as described in subsections 14.04.040.E, 14.04.040.F, or 14.04.040.G, the city may require the applicant to extend the wastewater main to such extent prior to obtaining utility service.
C. All public wastewater mains shall be placed within a dedicated public street. Where no public street is available and upon approval by the director, a public wastewater main may be installed within a dedicated municipal utility easement. Said easement shall not be less than 20 feet in width and shall be contained within a single parcel of land. The easement shall increase by ten feet in width for each utility main added to the easement beyond a single main. All mains shall be centered in the available easement space. Unless otherwise allowed by the city, all utility easements in a subdivision, not within a public or private street, shall be within a common element. The easement width required may increase with a main deeper than standard. In such instance, the easement shall be perpetual in nature and unless otherwise approved by the director, shall be exclusive to the city. Proper access by city personnel to all areas within the easement must be provided. No building, structures, fences, trees, shrubs, or other improvements that interfere with its use by the city, can be placed within the easement. The city reserves the right to operate, maintain, repair, replace and/or change the size and/or number of wastewater mains and appurtenances within such easement. All such easements shall be granted to the city in a form and manner that is acceptable to the city.
D. Unless otherwise approved by the director, a property shall not operate or otherwise use a septic system when such property lies within 400 feet of the city's wastewater system. The 400 feet length shall be measured from the closest point of that property to the point of connection from an existing, active and accessible city main and, generally, route through existing or future streets or, as determined by the department, other areas appropriate for a main. For any septic system installed on a property on or after January 1, 2023, a cleanout and sanitary sewer lateral shall be designed and constructed that complies with adopted standards and enables the property to disconnect from the septic system and connect to a city wastewater main and that cleanout and sanitary sewer lateral must be shown on civil improvement plans for the property that are accepted by, and on file with, the city. If deemed in the best interest of the city, the director may require the owner of such property to abandon all septic systems in accordance with applicable federal, state, and local requirements, perform a wastewater main extension and establish wastewater service from the city in accordance with the city's requirements.
E. Unless otherwise approved by the director, wastewater service must be obtained from the city whenever an undeveloped property initiates development through the city and such property lies within 400 feet of the city's wastewater system. In such instance, a wastewater main extension shall be required and must be made in accordance with the city's requirements.
F. In such instance where a parcel map is being proposed and offsite improvements are required as a condition of approval of such map, a wastewater main extension shall be required whenever the city's wastewater system lies within the resulting calculation of 400 feet multiplied by either the total number of lots created by recordation of such map of such parcel of land or the maximum number of lots that could be created based on then-current zoning, whichever number of lots is greater. Where consecutive parcel maps are being proposed, a main extension shall be required whenever the city's wastewater system lies within the resulting calculation of 400 feet multiplied by either (1) the total number of lots created by the recordation of the initial and all consecutive parcel maps combined or (2) the maximum number of lots that could be created based on then-current zoning of the parcels of land in the initial and all consecutive parcel maps combined for those parcels of land, whichever number of lots is greater. However, final determination, including application of this requirement, shall be made by the director.
G. In such instance where a tentative map or planned unit development is being proposed and no city wastewater main exists contiguous to the property, a wastewater main extension shall be required and must be made in accordance with the city's requirements.
H. Unless otherwise approved by the director, not more than one lot or other parcel of subdivided land shall be served by a single service connection. A single customer shall be responsible for payment of wastewater bills for each such service. Additionally, where the city provides wastewater service to a single lot or other parcel of subdivided land, the same customer shall be responsible for payment of both the water and wastewater bill.
1. Exception: In the case of a commercial subdivision whereby a single service line or service lines provide service to multiple lots or other parcels of subdivided land, a single customer shall exist in the form of a property owner's association. Said property owner's association shall be responsible for payment of all water and wastewater bills associated with such service(s). Additionally, the subdivision shall record a declaration of covenants, conditions and restrictions (CC&Rs) in the office of the Clark County recorder, which designates that all of the lot owners in the subdivision own an undivided interest in the private water and wastewater facilities, and that all of the lot owners must participate in the cost of the operation and maintenance of such private systems.
I. Where multiple services are provided to a single lot or other parcel of subdivided land, a single customer shall be responsible for payment of wastewater bills for all such services.
J. When a wastewater main extension is required, the director reserves the right to dictate the size, length and capacity of such wastewater main. The applicant may apply for partial cost reimbursement through the establishment of a refunding agreement, as outlined in this title and department service rules.
K. When a connection is made to any main, the main frontage fee is assessed in accordance with this title and department service rules. A minimum charge shall apply to any parcel having less than 60 feet of chargeable frontage.
L. All wastewater mains and main extensions must be designed and constructed in accordance with the city's adopted standards.
M. Before a wastewater main, service line, or connection is allowed to be placed into service, it shall be tested to the satisfaction of the city.
N. The granting of a certificate of occupancy does not relieve the developer of its obligations relative to the construction of the wastewater main extension; nor does it imply that the mains have been properly constructed or accepted by the city.
O. Upon completion of a wastewater main extension by a customer or subdivider, the customer or subdivider shall furnish the department a valid bill of sale conveying title to the city for such main and appurtenances, to include service lines, rights-of-way, and/or easements. Upon transfer of such title, the city reserves the right to provide direct or indirect service to any customer through the use of such wastewater mains and appurtenances.
P. The developer is responsible to correct any defects or failures that occur relative to the design and construction of the wastewater main extension, within a period of one year from the date of acceptance of the work by the city. The developer shall, at the developer's own expense, make good such defects and failures and make all replacements and adjustments required, in accordance with adopted standards. All repairs shall be subject to the approval of the city. Furthermore, developer is at no time relieved of any obligation or responsibility it may have by law, including but not limited to damages for latent deficiencies, injury to real or personal property or injury to or wrongful death of a person.
Q. The developer shall indemnify, defend and hold harmless the city, its officers, agents, volunteers, and employees, against and from any and all liability, loss, damage, claims, fines, demands, causes of action, costs, expenses, and judgments of whatsoever nature, including but not limited to reasonable costs of investigation, reasonable attorneys' fees and expenses, all reasonable expert witness fees and expenses, and all court or arbitration or other alternative dispute resolution costs which result from injury to or death of any persons whomsoever, and/or against and from damage to or loss or destruction of property whatsoever when such injury, death, loss, destruction or damage is due to or arises in connection with or as a result of any work done by the developer, its contractors, agents and subcontractors in connection with the construction of the main and/or arises out of or in connection with developer's, or its contractors' and subcontractors' performance or failure to comply with the requirements of this title or the department's service rules.
(Ord. No. 3905, § 8, 9-13-2022; Ord. 2798, § 3, 1-20-2009; Ord. 2676, § 4 (part), 2008; Ord. 2536, § 24, 2006)