Responsibility for selection of methods of construction contracting management.
R.I. Gen. Laws § 37-2-39
in effect37-2-39. Responsibility for selection of methods of construction contracting management.
The chief purchasing officer shall issue regulations providing for as many alternative
methods of management of construction contracting as he or she may determine to be
feasible, setting forth criteria to be used in determining which method of management
of construction is to be used for a particular project, and granting to the purchasing
agent, or the purchasing agency responsible for carrying out the construction project,
the discretion to select the appropriate method of construction contracting for a
particular project, provided, however, that the chief purchasing officer shall execute
and include in the contract file a written statement setting forth the facts which
led to the selection of a particular method of management of construction contracting
in each instance.
P.L. 1989, ch. 526, § 2.