Sec. 75-203. - Applications for approval.
(a) Concept plan and consultation meeting. Before a stormwater management permit application is deemed complete, the stormwater director or owner may request a consultation on a concept plan for the stormwater management system. This consultation meeting should take place prior to submitting the preliminary plan of subdivision, special use rezoning or other early step in the development or redevelopment process. The purpose of this meeting is to discuss generally the stormwater management system necessary for the proposed development or redevelopment, as well as to discuss and assess constraints, opportunities, and potential approaches to stormwater management system before formal site design engineering is commenced. The meeting is not intended to provide a total review of the final development plan. Local watershed plans, and other relevant resource protection plans may be consulted in the discussion of the concept plan. To accomplish this goal, the following information should be included in the concept plan, which should be submitted to the stormwater director at least five business days in advance of the consultation meeting:
(1) Existing conditions/proposed site plans. Existing conditions and proposed site layout sketch plans, which illustrate at a minimum: existing and proposed topography; perennial and intermittent streams; existing and proposed drainage conveyances; existing stormwater management systems; mapping of predominant soils from soil surveys (when available); boundaries of existing predominant vegetation and proposed limits of clearing and grading; and location of existing and proposed roads, buildings, parking areas and other impervious surfaces.
(2) Natural resources inventory. A written and/or graphic inventory of the natural resources at the site and surrounding area as it exists prior to the commencement of the project. This description should include a discussion of soil conditions, forest cover, geologic features, topography, wetlands, and native vegetative areas on the site, as well as the location and boundaries of other natural feature protection and conservation areas such as lakes, ponds, floodplains, stream buffers and other setbacks (e.g. drinking water well setbacks, septic setbacks, etc.). Particular attention should be paid to environmentally sensitive features that provide particular opportunities or constraints for development or redevelopment.
(3) Stormwater management system concept plan. A written or graphic concept plan of the proposed stormwater management system including the location of floodplain/floodway limits; relationship of site to upstream and downstream properties and drainages; and preliminary location of proposed stream channel modifications, such as bridge or culvert crossings.
(b) Assessment of impact. Each concept plan shall include an assessment of post construction stormwater impacts upon downstream and upstream properties. The assessment of stormwater quality and quantity impacts shall be based on the standards contained within this ordinance, at a minimum.
(1) Assessment and control of stormwater quality impacts. All stormwater management systems proposed to be include in any development or redevelopment, not otherwise exempt or excluded, shall assess and satisfy the applicable stormwater quality management requirements as indicated in section 75-302 of this ordinance, at a minimum.
(2) Assessment and control of stormwater quantity impacts. All stormwater management systems proposed to be include in any development or redevelopment, not otherwise exempt or excluded, shall assess and satisfy the applicable stormwater quantity management requirements as indicated in section 75-303 of this ordinance, at a minimum. An appropriately qualified professional for the owner must prepare the assessment of stormwater quantity impacts for review by the stormwater director. The assessment of upstream impacts must be provided, at a minimum, for property or properties located immediately upstream and/or adjacent to the proposed development or redevelopment. The stormwater director shall require that the impact assessment be extended for properties further upstream if site-specific conditions may cause an unreasonable impact on those properties further upstream. The assessment of downstream impacts shall be made by evaluating a site's contribution to stormwater runoff to a "suitable downstream point" considering the following guidelines:
a. A point downstream where the proposed site development or redevelopment represents less than ten percent of the total watershed area draining to that point (ten percent guideline).
b. A point downstream where drainage from the development or redevelopment site enters a Federal Emergency Management Agency (FEMA) established floodway.
c. A point where the stormwater director knows of no existing stormwater problems that the proposed development or redevelopment is likely to exacerbate.
d. A point where there are no public road crossings or other public infrastructure that may be adversely impacted by an increase in runoff from the proposed development or redevelopment.
This determination shall not alter any requirements related to stormwater quality management. These guidelines are intended to avoid unreasonable impacts wherever they might occur.
(c) Stormwater management permit application. The stormwater management permit application shall detail how development or redevelopment stormwater runoff will be controlled and managed and how the proposed project will meet the requirements of this ordinance. All such plans shall be prepared by a qualified registered state professional engineer, surveyor or landscape architect, and the engineer, surveyor or landscape architect shall perform services only in their area of competence, and shall verify:
(1) That the design of the stormwater management system meets the submittal requirements for complete applications;
(2) That the designs and plans are sufficient to comply with applicable standards and policies found in the design manual; and
(3) That the proposed stormwater management system ensures compliance with this article.
The submittal shall include all of the information required in the submittal checklist established by the stormwater director.
(d) As-built plans and final approval. Upon completion of a project and before a certificate of compliance, as defined in G.S. 160D-1116, shall be granted by the building inspector, the owner shall, except as provided for in subsection (e) of this section, certify that the completed project is in accordance with the approved stormwater management system, and shall submit actual as-built plans for the entire stormwater management system once construction is completed. The as-built plans shall show the final design specifications for the entire stormwater management system, including the field location, size, depth, and planted vegetation of all structural BMPs and other measures, controls, conveyances and devices, as installed. The designer of the stormwater management system shall certify, under seal, that the as-built stormwater management system is in compliance with the approved stormwater management system and with the requirements of this ordinance. A final inspection and approval by the stormwater director shall occur upon receipt of adequate as-built records.
(e) Other permits. No certificate of compliance shall be issued by the building inspector working in consultation with the stormwater director without final, as-built plans and a final inspection and approval by the stormwater director, except where multiple units are served by the stormwater management system, in which case the building inspector may elect to withhold a percentage of certificates of compliance until as-built plans are submitted and approved by the stormwater director.
(f) Variances. The board of adjustment shall hear and decide requests for variances from the stormwater director or their designee in the enforcement of chapter 75, article IV, post construction stormwater, pursuant to G.S. ch. 160D, arts. 4 and 14 and UDO section 3.2.16.A—G.
(Ord. No. 4618, § 1, 5-19-08; Ord. No. 24-0425, § 2, 9-16-24)