Additional requirements, conditions, and obligations
Seattle Mun. Code § 5.75.050
in effect5.75.050 - Additional requirements, conditions, and obligations
A. Within 30 days of the issuance of a certificate of occupancy by the City for an eligible investment project, the conditional recipient must file with the Director:
1. A description of the work that has been completed and a statement that the eligible investment project qualifies the property for a sales and use tax deferral under this Chapter 5.75;
2. A statement of the new affordable housing to be offered as a result of the conversion of underutilized commercial property to multifamily residential use including identification of the specific dwelling units to be offered as affordable housing and the monthly rent charged for each, and a statement of the total number of dwelling units to be offered as a result of the conversion of underutilized commercial property to multifamily residential use; and
3. A statement that the work has been completed within three years of the issuance of the conditional certificate of program approval.
B. Within 30 days after receipt of the statements required under subsection 5.75.050.A, the Director must determine and notify the conditional recipient in a letter as to whether the work completed and the affordable housing to be offered are consistent with the application and the conditional certificate of approval, and the investment project continues to qualify for a tax deferral under this Chapter 5.75. The conditional recipient must notify the Washington State Department of Revenue within 30 days from receiving the determination from the Director that the investment project continues to qualify for a tax deferral under this Chapter 5.75.
C. The Director must notify the conditional recipient within 30 days after receipt of the statements required under subsection 5.75.050.A that a tax deferral under this Chapter 5.75 is denied if the Director determines that:
1. The work was not completed within three years of the conditional certificate of program approval;
2. The work was not constructed consistent with the application or other applicable requirements;
3. The affordable housing units to be offered are not consistent with the application and criteria of this Chapter 5.75; or
4. The owner's property is otherwise not qualified for a sales and use tax deferral under this Chapter 5.75.
D. If the Director finds that the work was not completed within the required time period due to circumstances beyond the control of the conditional recipient and that the conditional recipient has been acting and could reasonably be expected to act in good faith and with due diligence, the Director may extend the deadline for completion of the work for a period not to exceed 24 consecutive months, and must notify the Washington State Department of Revenue of the extension.
E. If the Director determines the conditional recipient is not entitled to a sales and use tax deferral under subsection 5.75.050.C, the conditional recipient may appeal the decision to the City's Hearing Examiner within 30 days after receipt of the denial. The appeal before the Hearing Examiner must be based upon the record made before the City with the burden of proof on the applicant to show that there was no substantial evidence to support the City's decision.
F. Upon denial of the sales and use tax deferral under subsection 5.75.050.C the Director shall notify the Washington State Department of Revenue, upon which taxes deferred under this Chapter 5.75 are immediately due and payable, subject to any appeal by the conditional recipient.
(Ord. 127181, § 1, 2025.)
Source: City of Seattle, Seattle Municipal Code and City Charter (Municode Library, library.municode.com)URL: https://library.municode.com/wa/seattle/codes/municipal_code?nodeId=TIT5REFITA_SUBTITLE_IITA_CH5.75SAUSTADECOHO_5.75.050ADRECOOBFetched: 11/1/2026