33.705.020 Neighborhood Contact Steps
A.
Neighborhood contact I. Neighborhood contact I requires the following notification and
posting steps:
1.
Notification. The applicant must contact via email or mail the neighborhood association,
district neighborhood coalition, and business association for the area, and any
neighborhood association, district neighborhood coalition, or business association within
400 feet of the proposal site. The email or letter must be sent at least 35 days, but not
more than one year, before applying for a land use review or building permit. A copy of
the email or letter, and a list of the email or postal addresses to which the email or letter
was sent, must be submitted as part of the application for a land use review or building
permit. The email or letter must contain the following information:
a.
The name, telephone number and email address of the applicant;
b.
The address of the site of the proposed development;
c.
A summary of the proposed development; and
d.
A site plan that includes the proposed development.
2.
Sign. The applicant must post at least one sign on the proposed development site at least
35 days, but not more than one year, before applying for a land use review or building
permit.
a.
A sign must be placed on each street frontage of the site. If the street frontage is
over 600 feet long, a sign is required for each 600 feet or fraction thereof. Signs must
be posted within 10 feet of a street lot line and must be visible to pedestrians and
motorists. Signs may not be posted in a public right-of-way. Signs are not required
along street frontages that are not improved and do not allow motor vehicle access.
b.
The required signs must remain on the site until a building permit is issued or one
year has passed since the application that triggers the sign requirement was
submitted, whichever is less, except that the required signs must be removed from
the site when required posting for a land use review occurs.
c.
The Director of Portland Permitting & Development has the authority to adopt
administrative rules to determine the size and layout of the sign.
d.
A photograph of the required signs posted on the site must be submitted as part of
the application for a land use review or building permit.
e.
The signs must contain the following information:
(1) The name, telephone number and email address of the applicant;
(2) The name and email address of the neighborhood association that includes the
site;
(3) The name, telephone number and email address of the district neighborhood
coalition that includes the site;
(4) A written summary of the proposed development;
(5) A site plan that includes the proposed development; and
(6) Procedural information provided by Portland Permitting & Development.
3.
Required information.
a.
The applicant must contact Portland Permitting & Development via email, or an
online information submittal tool, at least 35 days, but not more than one year,
before applying for a land use review or building permit. The email, or online
submittal, must contain the following information:
(1) The name, telephone number, and email address of the applicant;
(2) The address of the site of the proposed development;
(3) A summary of the proposed development; and
(4) A site plan that includes the proposed development.
b.
The following information must be submitted as part of the application for a land use
review or building permit:
(1) A copy of the email or letter that was sent as required by Paragraph A.1.;
(2) A list of the email or postal addresses to which the email or letter required by
Paragraph A.1.was sent;
(3) A photograph of the sign required by Paragraph A.2. posted on the site;
(4) A signed statement certifying that the required email or letter was sent, and the
required signs were posted, at least 35 days, but not more than one year,
before applying for a land use review or building permit.
B.
Neighborhood contact II. Neighborhood contact II requires the following meeting, notification
and posting steps:
1.
Notification. The applicant must contact via email or mail the neighborhood association,
district neighborhood coalition, and business association for the area, and any
neighborhood association, district neighborhood coalition, or business association within
400 feet of the proposal site. The email or letter must be sent at least 35 days, but not
more than one year, before applying for a land use review or building permit. A copy of
the email or letter, and a list of the email or postal addresses to which the email or letter
was sent, must be submitted as part of the application for a land use review or building
permit. The email or letter must contain the following information:
a.
The name, telephone number and email address of the applicant;
b.
The address of the site of the proposed development;
c.
The date, time and location of the required public meeting; and
d.
A summary of the proposed development; and
e.
A site plan that includes the proposed development.
2.
Sign. The applicant must post at least one sign on the proposed development site at least
35 days, but not more than one year, before applying for a land use review or building
permit.
a.
A sign must be placed on each street frontage of the site. If the street frontage is
over 600 feet long, a sign is required for each 600 feet or fraction thereof. Signs must
be posted within 10 feet of a street lot line and must be visible to pedestrians and
motorists. Signs may not be posted in a public right-of-way. Signs are not required
along street frontages that are not improved and do not allow motor vehicle access.
b.
The required signs must remain on the site until a building permit is issued or one
year has passed since the application that triggers the sign requirement was
submitted, whichever is less, except that the required signs must be removed from
the site when required posting for a land use review occurs.
c.
The Director of Portland Permitting & Development has the authority to adopt
administrative rules to determine the size and layout of the sign.
d.
A photograph of the required signs posted on the site must be submitted as part of
the application for a land use review or building permit.
e.
The signs must contain the following information:
(1) The name, telephone number and email address of the applicant;
(2) The name and email address of the neighborhood association that includes the
site;
(3) The name, telephone number and email address of the district coalition that
includes the site;
(4) The date, time and location of the required public meeting;
(5) A written summary of the proposed development;
(6) A site plan that includes the proposed development; and
(7) Procedural information provided by Portland Permitting & Development.
3.
Meeting. The applicant must schedule and attend one public meeting. Until January 1,
2029, the applicant is not required to schedule or attend a meeting if the development
includes a residential use. Notes from the meeting and an explanation of any changes
made to the proposal as a result of comments received at the public meeting must be
emailed or mailed to the neighborhood association, district neighborhood coalition,
business association, school district and any meeting attendees who provide an email or
postal address, before an application for a land use review or building permit can be
accepted. The meeting must:
a.
Be held at least 14 days before applying for a land use review or a building permit,
and at least 14 days after sending the email or letter and posting signs required by
Paragraphs B.2. and B.3.
b.
Be held at a location within the neighborhood where the proposed development is
located or at a location that is not more than two miles from the boundary of the
neighborhood within which the proposed development is located and within the
boundaries of the district neighborhood coalition in which the proposed
development is sited. Meetings may be held in person, remotely using online video
conferencing technology, or a combination of both;
c.
Be held at a time between 6 p.m. and 9 p.m. Monday through Friday, or between 1
p.m. and 6 p.m. on Saturday or Sunday, or during a scheduled neighborhood
association meeting and which does not conflict with a scheduled neighborhood
association meeting unless held in conjunction with a neighborhood association
meeting;
d.
Be open to the public; and
e.
Be in a location that provides access to all members of the public. If requested by a
member of the public at least three days prior to the meeting, the applicant must
provide language services, alternative formats, auxiliary aids, or other reasonable
requests that ensure barrier free access.
4.
Required information.
a.
The applicant must contact Portland Permitting & Development via email, or an
online information submittal tool, at least 35 days, but not more than one year,
before applying for a land use review or building permit. The email, or online
submittal, must contain the following information:
(1) The name, telephone number, and email address of the applicant;
(2) The address of the site of the proposed development;
(3) A summary of the proposed development; and
(4) A site plan that includes the proposed development.
b.
The following information must be submitted as part of the application for a land use
review or building permit:
(1) A copy of the email or letter that was sent as required by Paragraph A.1.;
(2) A list of the email or postal addresses to which the email or letter required by
Paragraph A.1.was sent;
(3) A photograph of the sign required by Paragraph A.2. posted on the site;
(4) A signed statement certifying:
•
That the required email or letter was sent at least 35 days, but not more
than one year, before applying for the land use review or building permit;
•
That the required signs were posted, at least 35 days, but not more than
one year, before applying for the land use review or building permit;
•
That the required meeting was held at least 14 days before applying for the
land use review or building permit, and at least 14 days after sending the
email or letter and posting the required signs; and
•
That the notes from the required public meeting were emailed or mailed to
the neighborhood association, district neighborhood coalition, business
association, school district and any meeting attendees who provide an email
or postal address, prior to applying for the land use review or building
permit.
(Adopted by Ord. No. 189488, effective 12/2/19; Amended by: Ord. No. 190076, effective 8/10/20; Ord.
No. 191609, effective 3/1/24.)
The City of Portland is committed to providing meaningful access. To request translation, interpretation,
modifications, accommodations, or other auxiliary aids or services, contact 311, Relay: 711.
503-823-4000: Traducción e Interpretación | Biên Dịch và Thông Dịch | अनुवादन तथा व्याख्या
口笔译服务 | Устный и письменный перевод | Turjumaad iyo Fasiraad
Письмовий і усний переклад | Traducere și interpretariat | Chiaku me Awewen Kapas
www.portland.gov/bps/accommodation