Effect of ORS 469.595 on applications and applicants
Or. Rev. Stat. § 469.601
in effect469.601. Effect of ORS 469.595 on applications and applicants
ORS 469.595 does not prohibit:
(1) The Energy Facility Siting Council from receiving and processing applications for site certificates for nuclear-fueled thermal power plants under ORS 469.300 to 469.563, 469.590 to 469.619 and 469.930; or
(2) An applicant for a site certificate under ORS 469.300 to 469.563, 469.590 to 469.619 and 469.930 from obtaining any other necessary licenses, permits or approvals for the planning or siting of a nuclear-fueled thermal power plant.
1981 c.1 §8
Source: Oregon Legislature (oregonlegislature.gov)URL: https://www.oregonlegislature.gov/bills_laws/ors/ors469.html#469.601Fetched: 10/20/2026