218-6. Demolition and Landscaping.
1. PROCEDURE. In the demolition of buildings or structures or parts thereof, work on the structural elements shall begin at the top and, except as regulated in this section, one story at a time shall be completely removed. No wall, chimney, equipment or column of material shall be allowed to fall in mass on a floor or other construction which may be caused to fall because of such practice, except that when the surrounding area is vacant and of sufficient size, and when permitted by the commissioner, the whole or part of a building or structure may be dropped or pulled down if no persons are exposed to the hazard of falling or flying materials. All walls, floorings and structural remnants shall be removed to a depth of 2 feet below the adjacent grade. 2. REMOVAL OF MATERIAL AND EQUIPMENT. All material and equipment removed from the elevated portions of any alterations, repair or demolition work shall be lowered to grade or other storage of disposal level by means of approved equipment or devices. Where a space on the ground or on a floor is railed off and openings in boundary walls closed, materials or equipment may be dropped into the space. This regulation shall not apply to demolition work in which the material is removed and stored or otherwise disposed of within a story height. 3. CHUTES. a. When a protected or enclosed space for the dropping of materials cannot be provided, or when so ordered by the commissioner, fully enclosed, inclining chutes of wood or metal of a size which will not readily cause their obstruction, shall be provided for the removal of material and debris. Open chutes may be used to lower dismantled false-work or lumber from a height not exceeding 30 feet, but all other material or equipment shall be lowered by means of approved equipment or devices. b. Enclosed chutes shall not extend in an unbroken line for more than 30 feet, but shall be equipped at intervals of 30 feet or less with stops to prevent descending materials from attaining dangerous speeds. The bottom of each chute shall be equipped with a gate or stop, with approved means for closing or regulating the flow of material. 4. SPRINKLING. All materials as handled under sub. 3 shall be sprinkled to minimize the dust. 5. PROTECTION OF THE PUBLIC AND WORKERS. Protection of the public and workers from falling material or equipment, or other hazards, and the covering of floor openings, other than those openings while in use during demolition, shall conform to the regulations of ch. 228. 6. TEMPORARY OCCUPANCY OF PUBLIC THOROUGHFARES. Permits for the temporary occupancy of public thoroughfares for the storage of materials, construction of sheds, roofs, fences and for other temporary guards, devices and equipment shall be obtained from the commissioner of public works, as regulated in ch. 115. 7. ABANDONMENT OF SEWER AND WATER CONNECTIONS. Any person, firm or corporation demolishing or moving a building or structure that is served by a private or public water or sewer system shall have such system disconnected and abandoned in accordance with s. 225-9. 8. REMOVAL OF MATERIALS, GRADING AND EROSION CONTROL. a. All materials not to be used for fill in excavated areas shall be removed from the premises as the demolition work progresses. b. To prevent a public hazard or the creation of a public nuisance, upon completion of demolition, the premises shall, unless a permit for new construction has been issued, be filled where necessary with soil or other approved inorganic material not greater than one foot in dimension and graded to the level of the lot grade adjoining the building site, with allowance made for settlement. c. Once graded, the premises shall be returned to an erosion-free and dust-free condition by utilizing suitable landscaping, grass, trees, shrubs or other planted ground cover, or by other suitable means approved of by the commissioner. If the premises is located in a downtown zoning district, compliance with s. 295-705-8-a shall be required. d. If an owner fails or neglects to comply with the provisions of this sub. within the time allotted by the commissioner, the commissioner may issue an order to the owner or the owner's agent to correct the violation. If the order expires before it is complied with, the commissioner may cause the premises to be restored to an erosion-free and dust-free condition. The cost of such action shall be charged against and be a lien upon the real estate and be assessed and collected as a special charge, as provided in s. 200-21-7. 9. PARTY WALL. When any building or structure adjoining a party wall is demolished, the owner of the demolished building or structure shall remove the anchors at the beam and joist end in the standing wall. All voids in such wall shall be filled with material consistent with the adjacent wall section. All plaster, furring strips, paneling, lathe, gypsum board and stair stringers shall be removed from the standing wall surface as directed and approved by the department. 10. REMOVAL OF DRIVEWAY APPROACHES. a. Pursuant to s. 115-25, whenever the commissioner of city development issues a permit for the demolition of all structures on a premises, and the demolition will result in the discontinuance of the use of an existing driveway, the removal of the driveway and restoration of the street pavement, curb, gutter and sidewalk shall be a condition of issuance of such permit. Such removal and restoration shall not be required whenever the owner has obtained a permit for new construction prior to demolition of the structure or structures and the existing driveway is necessary for proper access to the structure described in the new construction permit. b. If an owner fails or neglects to comply with the provisions of par. a within the time allotted by the commissioner, the commissioner of neighborhood services may issue an order to the owner or the owner’s agent to correct the violation. If the order expires before it is complied with, the commissioner may cause the driveway to be removed and cause the restoration of the street pavement, curb, gutter and sidewalk. The cost of this action shall be charged against and be a lien upon the real estate and be assessed and collected as a special charge.
Ask a question about Milwaukee law
Corpus searches the Milwaukee sections it holds and shows the ones that match, with their citations. Free, no sign-in.