Prerequisites to approval of terminal construction.
San José Municipal Code § 25.04.350
in effect25.04.350 - Prerequisites to approval of terminal construction.
In addition to the prerequisites for terminal building construction specified in Sections 25.04.310, 25.04.330, and 25.04.710 of this chapter, the following requirements shall also apply:
A. New terminal facilities shall only be constructed when the city has obtained and approved adequate written documentation which assures that:
1. The funding of the costs of development, maintenance, and operation of such facilities will be paid by the users of the facilities, in accordance with standard city-established airline rates and charges, agreements, and financing documentation, so as to continue existing city practice and policy that no city general funds are utilized for airport development; and
2. The city complies with federal law and regulations pertaining to competition and to the city's competition plan for the airport.
B. The city manager shall cause a review of the airline leases and rate-setting methodologies to be conducted in order to assure that the agreements are appropriate to properly operate the airport and to finance airport projects in the 1997 Airport Master Plan.
(Ords. 25528, 26516.)