Sec. 35-F126. - Substantial Improvement/Substantial Damage (SI/SD) Determination.

(a) The following items may be excluded from SI/SD determinations: (1) Basic building maintenance, not to exceed two thousand dollars ($2,000.00). (Public Works may review this application, but no Floodplain Development Permit (FPDP) will be required.) (2) Clean-up and trash removal following structure damage. (3) Carpeting and re-carpeting installed over finished flooring such as wood or tiling. (Public Works may review this application, but no Floodplain Development Permit (FPDP) will be required.) (4) Plug-in appliances such as washing machines, dryers, and stoves. (5) Outside improvements, including landscaping, irrigation, sidewalks, driveways, fences, yard lights, swimming pools, pool enclosures, sewer line replacement/repairs and associated tunnel under the foundation for such repairs, and detached accessory structures (e.g., garages, sheds, and gazebos). (6) Costs for land surveying, plan and specification preparation, and permitting and inspection fees. (7) Costs to temporarily stabilize a building so that it is safe to enter to evaluate and identify required repairs. (8) Costs required for the minimum necessary work to correct existing violations of health, safety, and sanitary codes. (b) The following items must be included in SI/SD determinations: (1) Materials and labor, including the estimated value of donated or discounted materials and owner or volunteer labor. (a) Donated or volunteer labor should be estimated based on the applicable minimum-hour wage scales for the skill and type of construction work that is done. (2) Site preparation (foundation excavation) related to the improvement or repair. (3) Demolition, partial demo for the purposes of the improvements, and construction debris disposal. (4) Improvements related to compliance with the Americans with Disabilities Act (ADA). (5) Construction management and supervision. (6) Sales tax and contractor's overhead and profit. (7) Structural elements and exterior finishes, including foundations, walls, exterior finishes, windows and exterior doors, roofing, solar panels and equipment, gutters, and downspouts, hardware, and attached decks and porches. (8) Interior finish elements, including floor finishes, bathroom tiling and fixtures, wall finishes, built-in cabinets, interior doors, interior finish carpentry built-in book cases and built-in furniture, hardware, and insulation. (9) Utility and service equipment, including heating, ventilation, and air conditioning (HVAC) equipment, plumbing fixtures and piping, electrical wiring, outlets, and switches, solar panels, light fixtures and ceiling fans, security systems, built-in appliances, central vacuum systems, water filtration, conditioning, and recirculation systems. (c) Cumulative Substantial Improvement (SI) (1) Building improvements shall be tracked over time and counted towards the SI/SD determination. Building permits may be denied if the proposed improvements result in accumulative improvement of fifty (50) percent or more. (2) Improvement cost and market value are required for determining whether proposed improvements are considered as SI. At the time of application for an FPDP, the applicant must provide the total construction cost (based on 35-F126(b) and the current market value. If the structure suffered a substantial damage the market value of the structure would be assessed the year prior to the damage. The construction cost will be divided into the market value to determine the percentage of the improvement cost relative to the market value. This percentage will be calculated prior to issuance of each FPDP for a particular structure. The percentages will accumulate for a ten-year period from the date of the initial FPDP. Bexar County Appraisal District (BCAD) Improvement/Building Values will be used unless the applicant provides an appraisal. Tables F126-1 and F126-2 illustrate this approach: Table F126-1. Tracking Cumulative Substantial Improvements Improvements within a 10-year Period Year | Elapsed Time from Initial Permit | Current Market Value at Time of Permit ($) | Cost of Improvement ($) | Cost as percentage of current market value (%) | Cumulative Percentage (%) 2020 | 0 year | $100,000 | $10,000 | 10% | 10% 2023 | 3 years | $110,000 | $33,000 | 30% | 40% 2026 | 6 years | $120,000 | $8,000 | 6.7% | 46.7% 2029* | 9 years | $130,000 | $10,000 | 7.7% | 54.4%* *The FPDP in 2029 will be denied since the cumulative percentage is ≥50% Table F126-2. Tracking Cumulative Substantial Improvements Improvements Beyond a 10-year Period Year | Elapsed Time from Initial Permit | Current Market Value at Time of Permit ($) | Cost of Improvement ($) | Cost as percentage of current market value (%) | Cumulative Percentage (%) 2020 | N/A | $100,000 | $10,000 | 10% | 10% 2023 | 0 years | $110,000 | $33,000 | 30% | 40% 2026 | 3 years | $120,000 | $8,000 | 6.7% | 46.7% 2032** | 12 years | $140,000 | $20,000 | 14.3% | 14.3% **Once a 10-year period has passed since the initial improvement FPDP, the next permit re-starts the 10-year period.