§ 49-193 — Permit required

Denver Revised Municipal Code (Supp. No. 147, Update 3: codified through Ordinance No. 0852-26, enacted July 13, 2026) · Denver Revised Municipal Code § 49-193

Corpus is an independent public-information project, not the official City of Denver website. Stable reference: corpuslaw.us/code/26350d1d-0573-4ab4-905c-058a7779ec1e

Sec. 49-193. - Permit required.

(a) It shall be unlawful for any person, firm or corporation, including the city, to disturb the ground or pavement in any public right-of-way including any streets or alleys within the city without first obtaining a written permit therefor from the manager. (b) The applicant for a permit, other than the city and franchisee, shall be licensed under this article to perform street cuts. All applicants, before the issuance of the permit, shall submit the following to the manager: (1) An application for a street cut permit on forms furnished by the city; (2) Evidence that the applicant is not delinquent in payments due the city on prior work; (3) Evidence of all permits or licenses required to do the proposed work, if licenses or permits are required under the laws of the state or ordinances of the city; (4) A satisfactory plan of work showing protection of the subject property and adjacent properties when a transportation and infrastructure safety representative determines such protection is necessary; (5) A plan for the protection of shade and ornamental trees and the restoration of turf when the city forester determines that damage may occur to such trees or turf; (6) Evidence that all orders issued by the department to correct deficiencies under previous permits issued under this article have been satisfied; (7) Payment of a permit fee under section 49-197; (8) A health and safety plan designed to assure protection of workers and the public, if a street cut is to be performed in a radium street. (c) The permit shall specify the period of time when the work shall be performed, and if the work is not completed within the period specified a new permit shall be obtained. (d) No permit issued under the provisions hereof shall be for more than one (1) excavation project. (e) Emergencies. Excavations may be started by a person authorized to perform street cuts prior to issuance of a permit when necessary for preservation of life or property, provided that the person, firm or corporation making such excavation shall apply to the manager for a permit on the first working day after such excavation is commenced. Even in emergency situations, notice shall be given immediately to the street closure section and the street maintenance section of the department of transportation and infrastructure. (f) A street cut permit shall not be required for sidewalk, driveway, curb cuts, curb and gutter, curb ramps or cross-pan construction. All other applicable permits shall be required.

(Ord. No. 492-91, § 1, 7-1-91; Ord. No. 549-96, § 3, 7-1-96; Ord. No. 39-20, § 108, 2-3-20)