25.05.355 - Early review DNS (optional DNS) process
A. Early review DNS process. If the City is lead agency for a proposal and has a reasonable basis for determining significant adverse environmental impacts are unlikely, the notice of application comment period may be used to obtain comments on both the notice of application and the likely threshold determination for the proposal. B. If the lead agency uses the early review DNS process specified in subsection 25.05.355.A, the lead agency shall: 1. State on the first page of the notice of application that it expects to issue a DNS for the proposal, and that: a. The early review DNS process is being used; b. This will be the only opportunity to comment on the environmental impacts of the proposal; c. The proposal may include mitigation measures under applicable codes, and the project review process may incorporate or require mitigation measures regardless of whether an EIS is prepared; and d. A copy of the subsequent threshold determination for the specific proposal may be obtained upon written request and provision of an address for notice; 2. List in the notice of application the conditions being considered to mitigate environmental impacts, if a mitigated DNS is expected; 3. Comply with the requirements for a notice of application and public notice in Sections 23.76.012, 23.76.042, and 23.76.062; and 4. Provide the notice of application and environmental checklist to: a. Agencies with jurisdiction, the Department of Ecology, affected tribes, and each local agency or political subdivision whose public services would be changed as a result of implementation of the proposal, and b. Anyone who requests a copy of the environmental checklist for the specific proposal in writing and provides an address for notice. C. If the lead agency indicates on the notice of application that a DNS is likely, an agency with jurisdiction may assume lead agency status during the comment period on the notice of application (Section 25.05.948). D. The responsible official shall consider timely comments on the notice of application and either: 1. Issue a DNS or mitigated DNS with no comment period using the procedures in subsection 25.05.355.E; or 2. Issue a DS; or 3. Require additional information or studies prior to making a threshold determination. E. If a DNS or mitigated DNS is issued under subsection 25.05.355.D.1, the lead agency shall send a copy of the DNS or mitigated DNS to the Department of Ecology, affected tribes, agencies with jurisdiction, those who commented, and anyone requesting a copy. A copy of the environmental checklist need not be recirculated.
(Ord. 123913, § 50, 2012; Ord. 119096, § 26, 1998.)
Ask a question about Seattle law
Corpus searches the Seattle sections it holds and shows the ones that match, with their citations. Free, no sign-in.