Sec. 214-37. - Specifications to be met.

The following specifications must be met before a road shall be considered for acceptance as a city street: A. Subgrade. (1) The subgrades shall be prepared in approved manner by excavating or filling, as required. Filling shall be done in layers not to exceed twelve (12) inches in depth, using suitable material, each layer to be consolidated by rolling before the next layer is placed. Stones in earth fill shall be well distributed, and no stone over four (4) inches in diameter shall be left within twelve (12) inches of the finished subgrade. (2) Wherever soft clay or spongy or other types of unsuitable soil which will not compact under rolling are encountered, such soil shall be removed and replaced with gravel or other approved material, which shall be compacted as specified above. Wherever soil is of such nature that it retains an excessive amount of moisture or where conditions do not afford ready natural drainage, subdrains and side drains shall be provided in accordance with the requirements of the City Engineer. Preparation of the subgrade shall be performed upon completion of required excavation, filling and the installation of utilities. Where roadways are in cut, they shall be brought to subgrade elevation for a width of at least two (2) feet wider than the finished pavement width, i.e., one (1) foot on either side. B. Surface drainage. A complete system of surface drainage, to the satisfaction of the City Engineer, including catch basins and manholes, shall be installed prior to the final construction of the subgrade. Catch basins and manholes shall comply with requirements of the Engineering Department drawings, Nos. CB-1 and CB-2. All pipe used shall comply with the general specifications of the city. C. Gravel course. Upon the prepared subgrade, finished parallel to and twelve (12) inches below the surface of the finished grade of the street, shall be spread a layer of run-of-bank gravel to a depth which, when thoroughly compacted, shall be eight (8) inches. The largest stone size permitted in this course is four (4) inches. This course shall be rolled with a ten-ton roller until thoroughly compacted. Inequalities in the surface shall be corrected and rolling continued as may be necessary for a satisfactory result and to the satisfaction of the City Engineer. D. Pavement. (1) Alternate No. 1. (a) Alternate No. 1 shall be used in all designed, commercial and industrial zones, also on primary residential roads, but may be used in all zones. Where roadways are in embankment, the fill shall extend to subgrade level and for a width of not less than six (6) feet outside the curbline, i.e., three (3) feet on each side. The total subgrade area shall then be thoroughly consolidated by repeated rollings, using a self-propelled roller weighing not less than ten (10) tons. Areas beyond the above-described lines shall be excavated or filled to the full width of the highway, satisfactory to the City Engineer. Rough subgrade shall be formed and compacted in accordance with City Engineer-approved drawings and work shall be performed within tolerance of one and one-half (1½) inches of indicated levels. [1] Fine grade course. Upon the completed bottom course, as specified above, a layer of crushed stone of a nominal size of one and one-half (1½) inches shall be spread to a depth which, when consolidated, shall be three (3) inches. This course shall be thoroughly rolled with a ten-ton roller until thoroughly compacted and no movement occurs under passage of the roller. Inequalities in the surface shall be corrected and rolling continued as may be necessary for a satisfactory result. When fine graded, the road shall have a crown of four (4) inches. [2] Undercoat. After rolling, hot asphalt cement shall be applied at a rate of one and one-half (1½) gallons per square yard over the stone surface by means of a pressure distributor. Asphalt shall not be applied to damp or dirty stone. Asphalt for this purpose shall conform to standard specifications for liquid asphalt eighty-five-percent penetration. Immediately after application of the asphalt, one-half-inch stone chips shall be spread to fill the voids, the surface then to be broomed and rolled. [3] Topcoat. A one-inch compacted thickness of asphalt concrete shall then be spread. Material for this course shall conform to State Highway Specifications for asphalt concrete, Reference File No. 109 or No. 121. This material shall be spread by means of an approved mechanical spreader and thoroughly rolled and compacted to the required thickness by a tandem steel wheel roller weighing not less than ten (10) tons. The finished grade prior to final surfacing shall be smooth and even and shall not vary more than three-eighths (⅜) of an inch in ten (10) feet from true profile and cross section or more than one-half (½) of an inch from true elevation. (b) All of Alternate No. 1 shall be to the satisfaction of the City Engineer. (2) Alternate No. 2. (a) Alternate No. 2 may be used only on secondary residential roads in all one-half-acre (R-20) or less residential zones. [1] Fine grade course. Upon the prepared subgrade which has been brought to the proper grade and thoroughly compacted, a layer of screened gravel shall be placed to bring to the true grade. This layer, when thoroughly compacted, shall not be less than two (2) inches. Stones in this screened gravel shall pass through a one-inch screen. The proportion of sand and stone shall be about sixty percent (60%) stone and forty percent (40%) clean sand. When fine grade is completed, ready for finished surface, there shall be a crown of four (4) inches. [2] Topcoat. Upon the completed fine grade base, a course of asphaltic concrete shall be placed which is to comply with the State Highway 121F mix consisting of: eight hundred (800) pounds of sand, seven hundred sixty (760) pounds of 1A stone, three hundred twenty (320) pounds of No. 1 stone and one hundred twenty (120) pounds of asphalt. Wherever feasible and practical, an approved mechanical spreader shall be used. When thoroughly compacted with not less than a ten-ton roller, it is to be not less than two (2) inches in thickness. The entire installation shall extend not less than six (6) inches on each side beyond the required road width for the purpose of receiving an asphaltic concrete curbing to be four (4) inches in height, nine (9) inches at the base and four (4) inches at the top. The finished grade prior to final surfacing shall be smooth and even and shall not vary more than three-eighths (⅜) of an inch in ten (10) feet from true profile and cross section or more than one-half (½) of an inch from true elevation. (b) All of Alternate No. 2 shall be to the satisfaction of the City Engineer. (3) Alternate No. 3. (a) Alternate No. 3 is allowable on secondary residential roads in RA-1 (one-acre) and RA-2 (two-acre) Zones only. [1] Gravel course and undercoat. Upon the prepared subgrade, finished parallel to and ten (10) inches below the surface of the finished grade of the street, shall be spread a layer of run-of-bank gravel to a depth which, when thoroughly compacted, shall be eight (8) inches. The largest stone size permitted in this course is four (4) inches. Upon this completed bottom course shall be applied, by pressure distributor, RC special cutback asphalt at a rate of three-fourths (¾) of a gallon to one (1) gallon per square yard. Immediately thereafter a cover of one-half-inch crushed stone at approximately fifty (50) pounds per square yard shall be applied. Rolling with a ten-ton roller shall continue until thorough compaction is acquired, all to the satisfaction of the City Engineer. [2] Topcoat. After twenty-four (24) hours, the surface of the above first course shall be broom-dragged and there shall be applied to this surface, by pressure distributor, RC-4 or RS-2 asphalt at a rate of one-half (½) gallon per square yard. Immediately thereafter a cover of one-half-inch crushed stone at approximately forty (40) pounds per square yard shall be applied and then rolled thoroughly with a ten-ton roller. The finished grade prior to final surfacing shall be smooth and even and shall not vary more than three-eighths (⅜) of an inch in ten (10) feet from true profile and cross section or more than one-half (½) of an inch from true elevation. (b) All of Alternate No. 3 shall be to the satisfaction of the City Engineer. E. Curbing. Where curbing is installed, all loose stone shall be removed from the area and a tack coat of RS-2 asphalt, for bonding, shall be applied. After curbs are installed, complete grading to top edges of curb shall be made, all to the satisfaction of the City Engineer.

Ask a question about Stamford law

Corpus searches the Stamford sections it holds and shows the ones that match, with their citations. Free, no sign-in.