Rights of medicaid provider or subcontractor; preliminary or final determination of overpayment
NMSA 1978, § 27-11-12
in effect27-11-12. Rights of medicaid provider or subcontractor; preliminary or final determination of overpayment
A. A medicaid provider or subcontractor may challenge:
(1) the department's preliminary or final determination of overpayment as:
(a) exceeding statutory authority;
(b) arbitrary or capricious;
(c) a failure to follow department procedure; or
(d) not supported by substantial evidence;
(2) the credentials of persons who participated in the audit or claims review; or
(3) the methodology or accuracy of the department's audit.
B. A medicaid provider or subcontractor may, but shall not be required to, conduct its own audit or sampling to challenge a preliminary or final determination of overpayment.
Laws 2019, ch. 215, § 10.
Source: New Mexico Compilation Commission (nmonesource.com)URL: https://nmonesource.com/nmos/nmsa-unanno/en/item/18527/index.do#!b/27-11-12Fetched: 10/20/2026