Cause of action for next lowest bidding qualified contractor.
R.I. Gen. Laws § 9-1-52
in effect9-1-52. Cause of action for next lowest bidding qualified contractor.
Whenever a contractor or subcontractor, having been awarded the contract as the lowest
qualified bidder, violates the state’s prevailing wage, a cause of action shall be
for the next lowest qualified bidder for any and all damages incurred as the result
of not being awarded the contract.
P.L. 1994, ch. 429, § 1.