Portable solar generation device -- Exemptions -- Requirements.
Utah Code § 54-15-601
in effect54-15-601. Portable solar generation device -- Exemptions -- Requirements.
(1) A portable solar generation device that meets the requirements of this part:
(a) is exempt from:
(i) the interconnection requirements described in Section 54-15-106; and
(ii) requirements to enter into an interconnection agreement under Section 54-15-103; and
(b) is not subject to the net metering program requirements under this chapter.
(2) A portable solar generation device shall include a device or feature that prevents the system from energizing the building's electrical system during a power outage.
(3) An electrical corporation:
(a) may not require a customer using a portable solar generation device to:
(i) obtain the electrical corporation's approval before installing or using the system;
(ii) pay any fee or charge related to the system; or
(iii) install any additional controls or equipment beyond what is integrated into the system; and
(b) is not liable for any damage or injury caused by a portable solar generation device.
Enacted by Chapter 250, 2025 General Session
Source: Utah Office of Legislative Research and General Counsel (le.utah.gov)URL: https://le.utah.gov/xcode/Title54/Chapter15/54-15-S601.html?v=C54-15-S601_2025050720250507Fetched: 10/26/2026