Contract changes authorized.
Neb. Rev. Stat. § 61-516
in effect61-516. Contract changes authorized.
A design-build contract, a progressive design-build contract, and a construction manager-general contractor contract may be conditioned upon later refinements in scope and price and may permit the department in agreement with the design-builder, progressive design-builder, or construction manager to make changes in the project without invalidating the contract.
Laws 2023, LB565, § 16.
Source: Nebraska Legislature (nebraskalegislature.gov)URL: https://nebraskalegislature.gov/laws/statutes.php?statute=61-516Fetched: 10/20/2026