25.16.080 - Certificate of approval—Application
A. Application
1. All applications for a certificate of approval shall be submitted to the District Board.
2. The following information must be provided for the application to be complete, unless the Board staff indicate in writing that specific information is not necessary for a particular application:
a. Building name and building address;
b. Name of the business(es) located at the site of the proposed work;
c. Applicant's name and address;
d. Building owner's name and address;
e. Applicant's telephone number;
f. The building owner's signature on the application, or a signed letter from the owner designating the applicant as the owner's representative, if the applicant is not the owner;
g. Confirmation that the fee required by 22.900G.010 has been paid;
h. A detailed description of the proposed work; including:
1) Any changes it will make to the building or the site,
2) Any effect that the work would have on the public right-of-way or other public spaces, and
3) Any new construction;
i. Four sets of scale drawings, with all dimensions shown, of:
1) A site plan of existing conditions, showing adjacent streets and buildings, and, if the proposal includes any work in the public right-of-way, the existing street uses, such as street trees and sidewalk displays, and another site plan showing proposed changes to the existing conditions,
2) A floor plan showing the existing features and a floor plan showing the proposed new features,
3) Elevations and sections of both the proposed new features and the existing features,
4) Construction details, and
5) A landscape plan showing existing features and plantings, and another landscape plan showing proposed site features and plantings;
j. Photographs of any existing features that would be altered and photographs showing the context of those features, such as the building facade where they are located;
k. One sample of proposed colors, if the proposal includes new finishes or paint, and an elevation drawing or a photograph showing the location of proposed new finishes or paint;
l. If the proposal includes new signage, awnings, or exterior lighting:
1) Four sets of scale drawings of proposed signage or awnings, showing the overall dimensions, material, design graphics, typeface, letter size, and colors,
2) Four sets of a plan, photograph, or elevation drawing showing the location of the proposed awning, sign, or lighting,
3) Four copies of details showing the proposed method of attaching the new awning, sign or lighting,
4) The wattage and specifications of the proposed lighting, and a drawing or picture of the lighting fixture, and
5) One sample of proposed sign colors or awning material and color;
m. If the proposal includes demolition of a structure or object:
1) A statement of the reason(s) for demolition,
2) A description of the replacement structure or object; and
n. If the proposal includes replacement, removal, or demolition of existing features, a survey of the existing conditions of the features that would be replaced, removed, or demolished.
3. The staff shall determine whether an application is complete and shall notify the applicant in writing within 28 days of the application being filed whether the application is complete or that the application is incomplete and what additional information is required before the application will be complete. Within 14 days of receiving the additional information, the staff shall notify the applicant in writing whether the application is now complete or what additional information is necessary. An application shall be deemed to be complete if the staff does not notify the applicant in writing by the deadlines in this section that the application is incomplete. A determination that the application is complete is not a determination that the application is vested.
4. The determination of completeness does not preclude the staff or the District Board from requiring additional information during the review process if more information is needed to evaluate the application according to the standards in this chapter and in any rules adopted by the Board, or if the proposed work changes. For example, additional information that may be required could include a shadow study or a traffic study when new construction is proposed.
B. An applicant may make a written request to submit an application for a certificate of approval for a preliminary design of a project if the applicant waives in writing the deadline for the decision on the certificate of approval for a subsequent desigin phase or phases of the project and the applicant agrees in writing that the Board decision on the preliminary design is immediately appealable by the applicant or any interested person of record. The staff may reject the request if it appears that approval of a preliminary design would not be an efficient use of staff or District Board time and resources, or would not further the goals and objectives of this chapter. To be complete, an application for a certificate of approval for a preliminary design must include the information listed above in subsection A2, subparagraphs a through h, i(i) through i(iii), j, m and n. A certificate of approval that is granted for a preliminary design shall be conditioned upon subsequent submittal of the final design and all of the information listed above in subsection A2, and upon obtaining a certificate of approval for final design, prior to issuance of permits for work affecting any building or property in the District.
C. If, before a certificate of approval is obtained, an application is made to the Seattle Department of Construction and Inspections for a permit for which a certificate of approval is required, the Director of the Seattle Department of Construction and Inspections shall require the applicant to submit an application to the District Board for a certificate of approval. Submission of a complete application for a certificate of approval to the District Board shall be required before the permit application to the Seattle Department of Construction and Inspections may be deemed to be complete. The Seattle Department of Construction and Inspections shall continue to process such application, but shall not issue any permit until a certificate of approval has been issued pursuant to this Chapter 25.16, or the time has expired for filing with the Director of the Seattle Department of Construction and Inspections the notice of denial of a certificate of approval.
D. After the Board has commenced proceedings for the consideration of any application for a certificate of approval for a particular alteration or significant change by giving notice of a meeting pursuant to this section or otherwise, no other application for the same or a similar alteration or significant change may be made until the application has been withdrawn or such proceedings and all appeals therefrom have been concluded, except than an application may be made for a certificate of approval for the preliminary design of a project and a later application made for a certificate of approval for a subsequent design phase or phases of the same project.
(Ord. 127099, § 76, 2024; Ord. 124919, § 202, 2015; Ord. 119121, § 8, 1998; Ord. 118181, § 15, 1996; Ord. 118012, § 122, 1996; Ord. 109125, § 11(part), 1980; Ord. 105462, § 5(b), 1976)