Sec. 18-89. - Contracts for public works or capital improvements.
(a) Any public work or capital improvement may be executed either by contract or by the city labor force, as may be determined by the city commission. There shall be a separate accounting as to each work or improvement. Before authorizing the execution by the city labor force of any work or improvement or phase thereof, the city manager shall submit to the city commission a description of the anticipated scope of work and related cost estimates. (b) All contracts for public works or capital improvements in excess of $25,000.00 shall be awarded to the lowest responsive and responsible bidder after public notice on the basis of competitive sealed bidding methods, as provided herein or as provided in applicable Florida Statutes, whichever is determined to be in the best interest of the city. For contracts for public works and improvements in excess of $25,000.00 where it is both practicable and advantageous for the city to specify all detailed plans, specifications, standards, terms and conditions so that adequate competition will result and award may be made to the lowest responsive and responsible bidder principally on the basis of price; provided, however, when a responsive, responsible non-local bidder submits the lowest bid price, and the bid submitted by one or more responsive, responsible local bidders who maintain a local office, as defined in City Code section 18-73, is within 15 percent of the price submitted by the non-local bidder, then that non-local bidder and each of the aforementioned responsive, responsible local bidder(s) shall have the opportunity to submit a best and final bid equal to or lower than the amount of the low bid previously submitted by the non-local bidder. Contract award shall be made to the lowest responsive, responsible bidder submitting the lowest best and final bid. In the case of a tie in the best and final bid between a local bidder and a non-local bidder, contract award shall be made to the local bidder. Notwithstanding the foregoing, the city manager may establish a pool of pre-qualified contractors for the city construction projects ("pilot program"). The prequalification pool of contractors for city construction projects pilot program ("pool"), will participate in an expedited, competitive sealed bidding process, as identified in Exhibit "A" [to Ord. No. 13625], which is deemed as being incorporated by reference herein. Notwithstanding the foregoing, the city manager may waive competitive sealed procurement methods by making a written finding, supported by reasons, that a valid emergency exists or that there is only one reasonable source of supply, which finding must be ratified by an affirmative vote of four-fifths of the city commission after a properly advertised public hearing. When competitive sealed procurement methods are waived, other procurement methods as may be prescribed by ordinance shall be followed, except for the cone of silence provisions. (c) Public notice shall be in accordance with the applicable Florida Statutes. (d) Award. (1) All contracts for public works or capital improvements which do not exceed $25,000.00 shall be awarded on the basis of competitive negotiations. (2) All contracts for public works or capital improvements of $25,000.00 or more shall be awarded by the city manager only upon certification of the results of the evaluation and the bid tabulation by the chief procurement officer as being in compliance with competitive sealed procurement methods or in accordance with applicable Florida Statutes. (3) All contracts in excess of $100,000.00 must be approved by the city commission upon recommendation by the city manager. The decision of the city commission shall be final. (4) The city commission or the city manager shall have the authority to reject any or all bids or portions of bids, and re-bid or elect not to proceed with the project. (5) When it becomes necessary in the opinion of the city manager to make alterations or modifications in a contract for any public work or improvement which increases the contract to a total amount in excess of $100,000.00, such alterations or modifications shall be made only when authorized by the city commission upon the written recommendation of the city manager. No such alteration shall be valid unless the price to be paid for the work or material, or both, under the altered or modified contract shall have been agreed upon in writing and signed by the contractual party and the city manager prior to such authorization by the city commission. (6) Copies of the city manager's award shall be delivered to the director of the department of resilience and public works and to the chief procurement officer. (7) The city manager shall submit to the city commission on a monthly basis a list of contracts for public works or capital improvements awarded by the city manager. (e) Small business enterprise ("SBE"). (1) Except where state or federal law, regulations, or grant requirements mandate to the contrary, and subject to reservations or limitations provided in state, federal, or city laws, regulations, or grant requirements, respondents must assign a minimum of 15 percent of the contract value to a respondent or to a construction related enterprise currently certified by Miami-Dade County as a Small Business Enterprise ("SBE"). Respondents shall place a specific emphasis on utilizing local small businesses from within the city's municipal boundaries. The adoption of these provisions in the procurement ordinance of the city will be deemed an adoption by the city, as herein modified, and as may be amended from time to time of the Miami-Dade County SBE Program, as set forth in section 10-33.01, section 10-33.02, Miami-Dade County Code. The definitions, program components, subcontractor goals, contract measures, certification requirements, enforcement and administrative remedies from section 10-33.02, of the Miami-Dade County Code, as amended, are deemed as being incorporated by reference herein. (2) Five percent of the bid amount shall be retained by the city for the SBE participation requirements until said requirements are fulfilled and verified by the city manager or authorized designee as being fulfilled within six months of contract completion; failure to satisfactorily meet, document, and present to the city manager or authorized designee the SBE requirements within six months of contract completion shall result in the forfeiture of the retained amount to the city. This five percent retainage is included within the ten percent retainage normally withheld by the city. (3) The respondent selected as the contractor shall have a third party independently verify and certify compliance with these requirements on a quarterly basis. Said third party shall be unaffiliated with the respondent and be properly licensed under the provisions of F.S. chs. 454, 471, 473, or 481. The person performing the verification shall have a minimum of two years of prior professional experience in contracts compliance, auditing, personnel administration, or field experience in payroll, enforcement, or investigative environment. The cost for this verification and certification shall be included in the related contract costs. SBE requirements shall apply only to contracts with a contract value greater than $100,000.00 and with an on-site labor component greater than or equal to 25 percent of the contract value. These SBE requirements shall apply to any competitively procured contract under this section unless: • It meets one of the exclusion provisions noted above; • The city manager or designee deems the requirements unfeasible prior to issuance of the competitive selection document in which case the requirements of this section will be stated as not being applicable in the competitive selection document; • It is disallowed by federal or state law; • Funding sources require alternate, contradictory or specifically exclude SBE participation requirements; • These requirements are waived by the city commission by resolution, prior to issuance of the competitive solicitation document, upon written recommendation of the city manager or manager's designee, when the commission finds this is to be in the best interest of the city, in which case the requirements of this section will be stated as not being applicable in the competitive selection document. (f) Local workforce participation requirements. (1) Except where state or federal law, regulations, or grant requirements mandate to the contrary, and subject to reservations or limitations provided in state, federal, or city laws, regulations, or grant requirements, respondents must employ the following minimum percentage requirements for on-site labor from persons residing within Miami-Dade County (an individual whose primary place of residence is within Miami-Dade County), for the duration of the project. City construction contracts with a construction cost of up to $250,000.00 shall have no local workforce participation requirement. Construction contracts with a construction cost of $250,000.00 or more but less than $500,000.00 shall have a minimum local workforce participation requirement of ten percent. Construction contracts with a construction cost of $500,000.00 or more but less than $750,000.00 shall have a minimum local workforce participation requirement of 15 percent. Construction contracts with a construction cost of $750,000.00 or more but less than $4,000,000.00 shall have a minimum local workforce participation requirement of 20 percent. Construction contracts with a construction cost of $4,000,000.00 or more shall have a minimum local workforce participation requirement of 40 percent. "Construction costs" as referenced herein shall mean the total or estimated cost to the owner of all elements of the project being awarded, including, at current market rates, (with reasonable and customary allowance for overhead and profit), the costs of labor and materials, and any equipment or supplies that have been specified in the competitive solicitation document, but not including compensation for the architect, engineer, landscape architect, surveyor, mapper, or similar professional consultants. Local workforce participation requirements must be met by new hires and "laborer" as referenced herein shall mean a person as defined by F.S. § 713.01, who is retained by the contractor. All local workforce participation percentage requirements listed above shall be applied on the construction project's on-site labor force. The contractor shall strive to employ a minimum of 50 percent of the aforementioned minimum local workforce participation percentage requirements from within the city commission district where the project is located (e.g. if the project is in District X and the minimum local participation percentage requirement is ten percent then the contractor shall make its best efforts to employ a minimum of five percent of the required local workforce from District X). The county residency of the onsite labor component will be subject to verification by the issuing department. (2) Five percent of the bid amount shall be retained by the city for the local requirements until said requirements are fulfilled and verified by the city manager or authorized designee as being fulfilled within three months of contract completion. Failure to satisfactorily meet, document, and present to the city manager or authorized designee the local workforce participation requirements within three months completion after the project has reached final completion, shall result in the forfeiture of the retained amount to the city. This five percent retainage is included within the ten percent retainage normally withheld by the city and will comply with percentages specified in F.S. § 218.735. (3) For contracts with a bid amount between $1,000,000.00 and $2,000,000.00, the contractor shall be required to hold one job fair within the local community for the purpose of encouraging local workforce participation. For contracts with a bid amount greater than $2,000,000.00, the respondent shall be required to hold two job fairs within the local community for the purpose of encouraging local workforce participation. The contractor shall coordinate job fairs and hiring initiatives with South Florida Workforce or a similar state chartered regional workforce development board acceptable to the city manager. (4) Bid and proposal documents to which a local workforce participation requirement goal has been applied shall require the contractor to develop and submit to the city, within 30 days of notification of award of the construction contract, a workforce plan (plan) outlining how the goal will be met and containing the following information and elements required by this section. The plan shall specify the total number of persons that will be used by the contractor, broken down by trade and labor category, minimum qualifications for each category, and the number of persons to be utilized in each category. The plan shall identify by name, address, and trade category of all persons proposed to perform work under the contract currently on the contractor's payroll or positions to be hired by the contractor, who reside within Miami-Dade County. The city will not enter into the contract until it receives the contractor's plan and deems the plan acceptable. An updated plan shall be submitted to the city's project manager on a monthly basis. In the event that during the contract period a new hire or a person identified in the plan as meeting the local workforce participation requirement goal is replaced, the city may require the contractor to immediately identify the replacement. Notwithstanding anything to the contrary above, the contractor may be relieved from the requirements of this provision, in part or in whole, if such contractor can demonstrate that it has utilized its best efforts to achieve the goal in accordance with the prescribed provisions under this section. (5) The respondent shall have a third party independently verify and certify compliance with these requirements on a quarterly basis. Said third party shall be unaffiliated with the respondent and be properly licensed under the provisions of F.S. ch. 454, 471, 473, or 481. The person performing the verification shall have a minimum of two years of prior professional experience in contracts compliance, auditing, personnel administration, or field experience in payroll, enforcement, or investigative environment. The cost for this verification and certification shall be included in the related contract costs. The city shall consider the contractor's adherence to the city's local workforce participation requirements within the past three years in making any future contract awards to which this section applies. The solicitation documents will include the contractor's past compliance with these requirements of the city. Local participation requirements shall apply only to public works or capital improvements contracts with a contract value greater than $250,000.00 and with an on-site labor component greater than or equal to 25 percent of the contract value. These local workforce participation requirements shall apply to any competitively procured contract under this section unless: • It meets one of the exclusion provisions noted above; • The city manager or designee deems the requirements unfeasible prior to issuance of the competitive solicitation document, in which case the requirements in this section will be stated as not being applicable in the competitive solicitation document; • It is disallowed by federal or state law or grant requirements; • Funding sources require alternate, contradictory or specifically exclude or disallow local workforce participation requirements; • These requirements are waived by the city commission by resolution, prior to issuance of the competitive solicitation document, upon written recommendation of the city manager or manager's designee, when the commission finds this is to be in the best interest of the city, in which case the requirements of this section will be stated as not being applicable in the competitive selection document. (g) Contractor work performance evaluation system ("contractor evaluation system"). (1) Firms, entities, or persons addressed in section 18-89 of the City Code who are performing construction work, public works, or capital improvements for the city or any city agency or instrumentality will be subject to the following contractor evaluation system. The city, through appropriate staff selected by the city manager or the city agency or instrumentality through appropriate staff selected by the director of the using agency or instrumentality, will utilize established regulations to evaluate construction contracts for all projects subject to competitive solicitations under F.S. § 255.20, as provided herein and/or all construction work awarded by the city commission or a using agency or instrumentality pursuant to the City Code. The staff evaluating the contract must include the city's or using agency's project manager(s) and/or task manager(s) and must include any owner's representative who acted for the city or the using agency or instrumentality. At the option of the city manager or the director of the using agency or instrumentality or their designees, the project manager(s) and/or task manager(s) may also serve on the staff evaluation group. This contractor evaluation system will consider the contractor's performance for the entire length of the contract and goods and services provided or produced by the contractor including any change orders. A copy of the completed evaluation shall be provided to the contractor's construction manager or superintendent, the chief procurement officer or designee, and the city manager or using agency or instrumentality director who executed the agreement. A final composite evaluation of the contractor's contract performance shall be developed by combining all the contractor's evaluations for the full length (duration) of the contract. The contractor's work performance on each construction contract must be evaluated by the using agency's project manager(s) and/or task manager(s). A work performance grade of 1 through 5 for each major type of construction project (i.e. vertical, horizontal, electrical, etc.) shall be based on an evaluation of the schedule, including milestone dates, management, and quality. The schedule rating shall be based on contractor's compliance with the contract schedule and contract budget. The management rating shall be based on an evaluation schedule with one evaluation at 50 percent completion, a second evaluation at or about 75 percent substantial completion, and a final evaluation upon contract close out. The management rating shall be based on the contractor's ability to manage all necessary project resources, contract schedule, and contract budget. The quality rating shall be based on the contractor's attention and concern to the established quality control plan and product quality. The project manager shall assign the quality rating to any subcontractor named in the agreement or its exhibits for any major type of work performed. For all construction work that results from construction plans, a constructability rating shall also be assigned. The constructability rating shall be based on the contractor's ability to develop practical, accurate, complete, and cost-effective staffing, materials, supplies, equipment, satisfactory work progress, and scheduling. (2) The rating system for all work types shall be on a 1 to 5 rating with 1 equating with poor performance and 5 representing outstanding performance. (3) Each contractor in a prequalified pool will be evaluated at the end of each contract year considering all previous project evaluations and any vendor non-performance for that contract year. (4) The chief procurement officer is authorized to administratively promulgate and implement evaluation regulations. Such regulations and any amendments will be reported to the city manager, city attorney, mayor, and members of the city commission in writing. Such regulations may fully effectuate all the procedures for this section and shall be consistent with the procurement code. (5) Contractors with poor project evaluations are subject to the possibility of a suspension, termination, or debarment imposed by the city in accordance with the procedures set forth in section 18-107 of the City Code and the evaluation regulations. (6) Furthermore, contractor's previous city evaluations for the prior three years shall be considered at the time of prequalification in any city construction contractor pool or for stand-alone projects for which that contractor is submitting a bid or proposal.
(Ord. No. 12271, § 2, 8-22-02; Ord. No. 12654, § 2, 2-10-05; Ord. No. 12780, § 2, 3-9-06; Ord. No. 13275, § 2, 7-14-11; Ord. No. 13331, § 2, 7-26-12; Ord. No. 13332, § 2, 7-26-12; Ord. No. 13493, § 2, 1-22-15; Ord. No. 13625, § 2, 9-8-16; Ord. No. 13792, § 1, 10-11-18; Ord. No. 14007, § 2, 6-10-21)