Sec. 35-132. - Plugging methods to be used.

(a) When the producing or protective casing is left in the well, a cement plug of sufficient volume to fill one hundred (100) feet shall be set in the producing or protective casing so that the center of the plug is opposite the surface casing shoe. Minimum fifty (50) feet cement plugs shall be set near the surface in the producing or protective casing and in the annulus between the surface casing and producing or protective casing. The required location of either plug set in the protective or production casing must be confirmed by tagging and confirmation that the annulus is plugged, either by tagging or successfully holding a five hundred (500) psi pressure test, is required. (b) Where there is no producing or protective casing above the shoe of the surface casing then a one hundred-foot cement plug shall be placed opposite the shoe of the surface casing to extend at least fifty (50) feet downward and a similar fifty (50) feet upward from the shoe of the surface casing. Sufficient time shall be allowed for this cement to harden enough so that it will sustain the weight of drill pipe or tubing to this depth. The operator shall feel for the top of the plug to determine that the top is at least fifty (50) feet above the shoe of the surface casing and is of sufficient hardness to hold the weight of the drill pipe or tubing to this depth. In the event the top of the plug is not fifty (50) feet upwards from the shoe, then a second cement application will be required and tested as above. After the plug at the shoe has been successfully completed then a minimum fifty-foot cement plug shall be set near the surface. If a retainer is set near the surface casing shoe as in method (c) below, then tagging of the plug is not required. (c) Where the protective or producing string of casing to be left in the well extends upwards from the shoe of the surface casing so as to prevent the above described method of abandonment, then the following procedure will be used. A packer or cement retainer shall be set near the top of any other casing within the surface casing and sufficient cement shall then be squeezed below the packer or retainer to theoretically extend to fifty (50) feet below the shoe of the surface casing and fill that portion up to twenty (20) feet above the packer or retainer with the cement. (d) Where well conditions prevent plugging of the well in accordance with above paragraphs (a), (b) and (c) of this section, the operator shall plug and abandon such well using any alternate method which may be proposed by the operator and approved by the superintendent. (e) Whenever operations under this section are employed then the following further requirements will be complied with: (1) When casing is to be shot or cut off and pulled, a blowout preventer to close off around the casing to be pulled shall be installed prior to shooting or cutting off the casing. (2) In all cases prior to cutting any casing, the annulus between the casing to be recovered and the surface string of casing will be tested to determine whether this annulus is dead or pressured. In the event it is pressured then no casing will be recovered until this pressure is released to zero and the annulus filled with mud-laden fluid. (3) The well shall have a safety valve installed on the top of the casing string before any casing is shot or cut off. This safety valve shall not be removed until the first joint of casing has been pulled and shall then be kept immediately at hand so that it may be, if needed, reinstalled. (4) The well shall be completely filled at all times with mud-laden fluid of not less than 9.5# per gallon during all casing and tubing operations. Periodic checks will be made of the mud fluid during displacing operations. (5) Operator shall have a responsible representative at the well site during the setting and tagging of cement plugs and during the casing pulling operations, to ensure that the procedures outlined in the "Notice of Intent to Plug and Abandon" filed with the railroad commission are complied with and to ensure that other provisions of this chapter are complied with.

(Ord. No. 18177, § 1, 4-11-1984)