§ 37.09 — STORMWATER MANAGEMENT PLAN REQUIREMENTS
Madison General Ordinances (Rev. 28, Update 3: codified through ORD-26-00040, published August 3, 2026) · Madison General Ordinances § 37.09
Corpus is an independent public-information project, not the official City of Madison website. Stable reference: corpuslaw.us/code/3c64bd63-871f-489c-a828-5c67576759f6
37.09 - STORMWATER MANAGEMENT PLAN REQUIREMENTS.
(1) Stormwater Management Plan Required. (a) Every applicant for a stormwater management permit shall submit a plan documenting the system(s) and measures proposed to control stormwater runoff from the site. Included in this stormwater management plan shall be a completed standard stormwater management summary template. This template shall be available at: https://www.cityofmadison.com/engineering/permits/stormwater-management-permit. The stormwater management plan shall be completed and sealed by a Professional Engineer currently licensed in the State of Wisconsin. (Am. by ORD-21-00073, 11-17-21) (b) Evidence of Financial Responsibility. The Administrative Authority may require a financial security instrument sufficient to guarantee complete construction of the stormwater management systems proposed in the stormwater management plan. (2) Plan Contents. Stormwater management plans shall satisfy all of the requirements in Sec. 37.09(3), and shall provide, at a minimum, the following information: (a) The summary template required in Sec. 37.09(1)(a) above, and a narrative describing the proposed project, including implementation schedule for planned practices; (b) Identification of the entity responsible for long-term maintenance of the project; (c) A topographic map of the site location, including the contiguous properties, existing drainage patterns and watercourses affected by the proposed development of the site and the existing vegetative cover; (d) A map showing drainage areas for each watershed area; (e) A summary of runoff peak flow rate calculations, by watershed area, including all of the following: 1. Pre-existing peak flow rates; 2. Post-construction peak flow rates with no detention; 3. Post-construction peak flow rates with detention; 4. Estimated runoff curve numbers (RCNs). For pre-development and post-development conditions, RCNs shall be consistent with the following: a. Pre-development RCNs shall be considered to be a maximum of Hydrologic Soil Group B. b. Post-development RCNs shall be considered to be a minimum of Hydrologic Soil Group C unless methods are taken to reduce compaction of the site. Approval of the proposed compact mitigation methods are at the discretion of the Administrative Authority and, if approved, shall require documentation by a Registered Professional Engineer in the State of Wisconsin. c. RCNs for redevelopment sites where soil has been previously disturbed shall not require the Hydrologic Soil Group to change from pre to post development as long as methods are taken to reduce compaction of the site and included on the plan set. (Cr. by ORD-25-00017, 3-20-25, Eff. 4-1-25) Hydrologic Soil Group A | B | C | D Woodland | 30 | 55 | 70 | 77 Grassland | 39 | 61 | 71 | 78 Cropland | 51 | 68 | 78 | 83 5. Time of concentration (Tc) used in calculations. (f) A complete site plan and specifications, sealed by the Professional Engineer who designed the stormwater management system(s) and measures. All plans and specifications shall be drawn to a legible scale, shall be clearly labeled, and shall include, at a minimum, all of the following information: 1. Property lines and lot dimensions; 2. All buildings and outdoor uses, existing and proposed, including all dimensions and setbacks; 3. All public and private roads, interior roads, driveways and parking lots and shall show traffic patterns and type of paving and surfacing material; 4. All natural and artificial water features, including, but not limited to lakes, ponds, streams (including intermittent streams), and ditches. Show ordinary high water marks of all navigable waters, 100-year flood elevations and delineated wetland boundaries, if any. If not available, appropriate flood zone determination or wetland delineation, or both, may be required at the applicant's expense; 5. Depth to bedrock; 6. Depth to seasonal high water table; 7. The extent and location of all soil types as described in the Dane County Soil Survey, slopes exceeding twelve percent (12%), and areas of natural woodland or prairie; 8. Existing and proposed elevations (referenced to USGS Vertical NAVD88 Datum); 9. Elevations, sections, profiles, and details as needed to describe all natural and artificial features of the project; 10. Soil erosion control and overland runoff control measures, including runoff calculations as appropriate; 11. Detailed construction schedule indicating the anticipated starting and completion dates of the development sequence; 12. Copies of permit or permit applications required by any other governmental entities or agencies; 13. Any other information necessary to reasonably determine the location, nature and condition of any physical or environmental features; 14. Location of all stormwater management practices; 15. All existing and proposed drainage features; 16. The location and area of all proposed impervious surfaces; 17. The limits and area of the disturbed area; 18. Seeding mixtures and rates, lime and fertilizer application rates, and kind and quantity of mulching for both temporary and permanent vegetative control measures. (g) Engineering designs and detailed drawings for all structural management practices; (h) If required under Sec. 37.09(3)(b), the plans to provide required oil and grease control; (i) If required under Sec. 37.09(3)(a), the plans to provide required sediment (TSS) removal; (j) If required under Sec. 37.09(3)(e), the plans to provide required infiltration; (k) A maintenance plan and schedule for all permanent stormwater management practices as recorded on the affidavit required in Sec. 37.11(2); (l) Where the area being developed is in or adjacent to an area prone to flooding, as determined by the Administrative Authority, the applicant shall provide detailed survey and proposed site plan information on the proposed lowest entrance openings to the building (including underground parking). Further, the applicant shall complete an analysis of the stormwater drainage conveyance system for the area as it relates to the proposed new building and shall certify to the Administrative Authority that the building has been designed to provide a minimum flood protection to the 100-year event by limiting the lowest entrance opening elevations. This plan and analysis shall be reviewed and accepted by the Administrative Authority and placed on file with the City Engineer. The elevations set under the above process are minimums and the Developer may be required to exceed the elevations by the Administrative Authority. These elevation requirements shall apply to all entrances to the proposed structure including access to underground parking. In the case where the entrance to subsurface parts of a building is served by a pumping system, the pumping plans shall be submitted to the Administrative Authority and shall be stamped by a Professional Engineer in the State of Wisconsin. These plans shall provide and document that the pump system can adequately control the anticipated flows that result from a 100-year storm event. Alternatively, the pumping plan may be certified by a Professional Engineer and the pump design and installation plan itself certified by a Master Plumber as defined by Wisconsin Statute; (m) A completion date for all proposed stormwater management devices to be constructed and in service on the site. Failure to complete the project and bring the devices into service by the approved date shall constitute a violation of this section. (n) Where the area being developed includes using existing privately maintained stormwater management practices to meet new stormwater management metrics, an inspection report completed within the last year showing the existing stormwater management practices are in good working condition shall be provided. If the inspection report shows the practices require maintenance, provisions shall be included within the proposed plan. (Cr. by ORD-25-00017, 3-20-25, Eff. 4-1-25) (3) Stormwater Management Performance Standards. The proposed design, suggested location and phased implementation of effective, practicable stormwater management measures as set forth in the stormwater management plan shall be designed, engineered, and sealed by a Professional Engineer licensed in the State of Wisconsin, and implemented to achieve the following results: (a) Sediment Control. 1. For new development, by design: Reduce, to the maximum extent practicable, total suspended solids load leaving the site by eighty percent (80%), based on the average annual rainfall, as compared to no runoff management controls. This shall requires the use of a continuous model such as SLAMM, P8 or equivalent, and the use of approved grain size distribution curves and rainfall data. These files are managed and maintained by the Wisconsin Department of Natural Resources and are available on its website (https://dnr.wi.gov/topic/stormwater/). No person shall be required to exceed an eighty percent (80%) total suspended solids reduction, for the site as a whole, to meet the requirements of this subdivision. The analysis needed for this shall use approved procedures and assume no re-suspension of particles. If the applicant proposes to use treatment devices in series, then the analysis shall require the use of a modeling program that provides for tracking of the particulates trapped by each device used in series. If a program tracking particulate distributions is not used, then the Administrative Authority shall not allow the use of serial redundant devices. 2. For redevelopment, by design: Reduce, to the maximum extent practicable, total suspended solids (TSS) loads leaving the redeveloped site by forty percent (40%), based on average annual rainfall, as compared to no runoff management controls. This shall require the use of a continuous model such as SLAMM, P8 or equivalent, and the use of approved grain size distribution curves and rainfall data. These files are managed and maintained by the Wisconsin Department of Natural Resources and are available on its website (https://dnr.wi.gov/topic/stormwater/). No person shall be required to exceed a forty percent (40%) total suspended solids reduction, for the site as a whole as compared to no runoff management controls, to meet the requirements of this subdivision except as noted below in Sec. 37.09(3)(a)3. for sites located in the Rock River TMDL watershed. The analysis needed for this shall use approved procedures and assume no re-suspension of particles. If the applicant proposes to use treatment devices in series, then the analysis shall require the use of a modeling program that provides for tracking of the particulates trapped by each device used in series. If a program tracking particulate distributions is not used, then the Administrative Authority shall not allow the use of serial redundant devices. 3. For redevelopment and/or resurfacing by design for sites located within the Rock River TMDL: Reduce, to the maximum extent practicable, total suspended solids (TSS) loads leaving the redeveloped or resurfaced site by eighty percent (80%), based on average annual rainfall, as compared to the existing conditions of the site prior to the proposed redevelopment and/or resurfacing. This shall require the use of a continuous model such as SLAMM, P8 or equivalent, and the use of approved grain size distribution curves and rainfall data. These files are managed and maintained by the Wisconsin Department of Natural Resources and are available on its website (https://dnr.wi.gov/topic/stormwater/). Changes in TSS loading as compared to the existing site are expected to be met from land use changes and stormwater management practices. This requirement shall be considered met if the eighty percent (80%) reduction requirement is met for the site or all new exposed parking areas and access drives that exceed 200 feet in length reach a sixty percent (60%) total suspended solids reduction, as compared to no controls. The analysis needed for this shall use approved procedures and assume no re-suspension of particles. If the applicant proposes to use treatment devices in series, then the analysis shall require the use of a modeling program that provides for tracking of the particulates trapped by each device used in series. If a program tracking particulate distributions is not used, then the Administrative Authority shall not allow the use of serial redundant devices. 4. Redevelopment projects that previously triggered new development TSS reduction levels of eighty percent (80%) since February 8, 2005 shall continue to be required to meet this higher level of treatment and are not eligible for the lower TSS reduction percentages described in paragraphs 2. and 3. 5. Public trails and sport courts, including public paved bike paths, walking paths or multi use paths that have pavement 20 feet or less in width and have a turf buffer or ditch/swale, shall be exempted from peak detention, infiltration and TSS requirements. For public properties or features that are open to the public via agreement, the TSS reduction requirements shall be exempted for sport courts if the sport court paved area is less than 5,000 square feet or there is a minimum of 30 feet of turf area as a buffer around the courts. (Cr. by ORD-25-00017, 3-20-25, Eff. 4-1-25) (b) Oil and Grease Control. For new development or redevelopment sites that include commercial or industrial land uses and all other land uses where the potential for pollution by oil and/or grease exists, the first one-half (0.5) inches of runoff will be treated using the best oil and grease removal technology available. Specifically, oil and grease control shall be required for all parking facilities exposed to the elements that have a cumulative number of parking stalls greater than or equal to forty (40) with all parking areas constructed since August 22, 2001 receiving treatment. Sites with exposed drive up windows or any other sites deemed high potential for oil and grease deposition by the Administrative Authority shall also receive treatment. The Administrative Authority may waive this requirement only when the applicant can demonstrate that the installation of such practices is not necessary. (c) Runoff Rate Control. 1. General. Runoff rate control is required for new development and redevelopment upon an incremental cumulative increase in new impervious area equal or exceeding twenty thousand (20,000) square feet. Incremental increases over a period of years since August 22, 2001, such that multiple small incremental increases in new impervious area eventually exceeds the twenty thousand (20,000) square foot criteria, shall be retroactively controlled once the cumulative increase in new impervious area meets or exceeds twenty thousand (20,000) square feet. Sites being developed within a Plat or CSM having a stormwater management plan previously approved for rate control at the Plat/CSM level, with rate control standards that include a maximum control requirement of the 10-year storm event, shall comply with 37.09(3)(c)2.e. and f. Sites being developed within a Plat or CSM having a stormwater management plan previously approved for rate control at the Plat/CSM level, with rate control standards that include a maximum control requirement of the 100-year storm event, shall comply with 37.09(3)(c)2.f. For sites noted above that are within developments that had some level of detention at the plat level, the required volume of detention to be provided shall be calculated by the following method: a. Determine the runoff from the undeveloped site in compliance with design storms used for the regional/plat runoff models when smaller than the standards of this ordinance. Otherwise, determine the runoff from the undeveloped site in compliance with the standards of this ordinance for the 10, 100 and 200 year events. b. Determine the runoff from the proposed site in the 10, 100 and 200 year events. c. Complete a TR-55 based analysis to determine the volume of detention storage theoretically required to detain the post development 10, 100 and 200 year storm events to the predevelopment discharge rates. d. If detention at the plat level is designed to meet 10 year runoff rate controls for developed lots and the proposed development does not exceed the curve number for the developed site in the plat stormwater management report, complete the following: for the site only, complete modelling calculations per 37.09(3)(c)1.a-c., then subtract the volume needed by the 10 year event from the volume needed by the 200 year event. The site shall provide detention volume equal to the difference in calculated volume. Design the detention device(s) to fill during the post development 100-year event. e. If detention at the plat level, is designed to meet 100 year runoff rate controls for developed lots and the proposed development does not exceed the curve number for the developed site in the plat stormwater management report, complete the following. For the site only, complete modelling calculations per 37.09(3)(c)1.a-c. Subtract the volume needed by the 10 year event from the volume needed by the 200 year event. The site shall provide detention volume equal to the difference in calculated volume. Design the detention device(s) to fill during the post development 100-year event. f. For Closed Watersheds, predevelopment modeling shall include closed watershed areas. Sites that drain to closed watersheds must be designed with: (i) an emergency drawdown or pumping plan, and (ii) detention storage capacity for back to back 100-year 24-hour design storms. g. For residential areas being re-platted prior to any development occurring on the lands and for which a regional stormwater management plan was approved at the level of the initial plat or preliminary plat meeting the detention requirements for the 100-year event, no recalculation or upsizing of the existing stormwater management features shall be required to accommodate the 200-year event provided the re-platted development pattern does not exceed the proposed CN in the original stormwater management plan and the re-plat occurs within 7-years of the effective date of this ordinance. If the CN for the re-platted area does increase above that submitted as part of originally approved submittal, the change in volume required to detain the additional impervious area to the 100-year event shall be provided on a lot by lot basis with distributed infrastructure. Hydrologic calculations for event driven analysis shall be completed according to the methodology described in the Natural Resources Conservation Service's Technical Release 55, "Urban Hydrology for Small Watersheds" (commonly known as TR-55), for analysis requiring average annual results SLAMM or other Technical Standards and Specifications as provided in Sec. 37.10(5). Runoff curve numbers for vegetated areas shall comply with 37.09(2)(e). The TR-55-specified curve numbers for other land uses shall be used. 2. New Development. All stormwater facilities for new development shall be designed, installed and maintained to effectively accomplish the following: a. Maintain predevelopment peak runoff rates for the 1-year, 24-hour storm event (2.49 inches over 24 hours duration using the MSE4 NRCS Rainfall Distribution). b. Maintain predevelopment peak runoff rates for the 2-year, 24-hour storm event (2.84 inches over 24 hours duration using the t4 NRCS Rainfall Distribution). c. Maintain predevelopment peak runoff rates for the 5-year, 24-hour storm event (3.45 inches over 24 hours duration using the MSE4 NRCS Rainfall Distribution). d. Maintain predevelopment peak runoff rates for the 10-year, 24-hour storm event (4.09 inches over 24 hours duration using the MSE4 NRCS Rainfall Distribution). e. Maintain predevelopment peak runoff rates for the 100-year, 24-hour storm event (6.66 inches over 24 hours duration using the MSE4 NRCS Rainfall Distribution). f. Maintain predevelopment peak runoff rates for the 200-year, 24-hour storm event (7.53 inches over 24 hours duration using the MSE4 NRCS Rainfall Distribution). g. Safely pass the 500-year, 24-hour storm event (8.94 inches over 24 hours duration using the MSE4 NRCS Rainfall Distribution). h. Pre-existing detention (intended or unintended) on the site shall be taken into account as part of proposed detention calculations. At a minimum, the pre-existing detention volume shall be estimated and shall be considered to be a base amount of storage required for the site prior to completing any pre- to post-storm rate matching, including capacity reductions from existing culverts/stormsewer leaving the site. Effectively the pre-existing detention volume shall be added to the volume required to meet the pre- to post-rate controls. i. Downstream system capacity shall be analyzed to determine the safe capacity of the off-site drainage system. No release rates in excess of this safe capacity shall be allowed. The existing safe release rates are one method that may be used to determine the pre-existing detention volume for the site. j. Overflow elevations shall be calculated through the development to assure that the 100-year event flows through the streets and is confined to the public Right-of-Way. Further the 500-year event flood elevation shall be routed through the development to determine flood elevations. The 500-year event is allowed to flood private property but lowest entrance elevations of structures shall be set to prevent structural flooding during the 500-year event. 3. Redevelopment. If the redevelopment project has a proposed impervious cover which reduces impervious cover for the total site area (measured by the parcel area) to 80% of the existing site impervious cover, then the site shall be considered to have met the Redevelopment runoff rate standards. For sites that are not reducing total impervious cover to this extent, they shall be required to meet the following criteria: a. Reduce peak runoff rates from the site by 15% compared to existing conditions during a 10-year design storm. b. Reduce runoff volumes from the site by 5% compared to existing conditions during a 10-year design storm. However, if, in the opinion of the Administrative Authority, this volume reduction requirement is not reasonably feasible due to conditions including, but not limited to, high groundwater, contaminated soils, contaminated groundwater, limitations of water reuse due to the anticipated land use, and inability to support a green roof due to structure reuse, this volume reduction requirement may be waived by the Administrative Authority. It is the Developer's responsibility to establish that conditions make volume reduction not reasonably feasible. c. The required rate and volume reductions shall be completed, using green infrastructure that captures at least the first ½ inch of rainfall over the total site impervious area. If additional stormwater controls are necessary beyond the first ½ inch of rainfall, either green or non-green infrastructure may be used. Calculations documenting achievement of this level of treatment shall utilize one of the methods detailed in the Dane County Stormwater manual. A link to that documentation is provided here: https://danecountystormwatermanual.com/doku.php?id=green___infrastructure. d. The following guidance shall be used in interpreting these requirements: i. Existing open space (not including green roofs or pervious pavement) shall be modeled with a curve number of 74 both pre and post development. ii. Documentation of the treatment capacity of a green roof shall be completed in accord with the methodology documented in the Dane County Stormwater Manual. A link to the specific method is provided here: https://danecountystormwatermanual.com/doku.php?id=green___roof. NOTE: This methodology is based upon the standard created by the State of Wisconsin Green Tier process. e. Regardless of how or what green infrastructure features are used to meet the above requirements (Sec. 37.09(3)(c)3.a., b. and c.), they shall require the recording of a maintenance agreement for the features against the appropriate parcel. 4. Flood Prone Watersheds. For lands known to the City Engineer to be within watersheds or subwatersheds experiencing flooding, development and redevelopment shall comply with the detention/storage and/or necessary system/pipe upgrade requirements identified in individual watershed plans. These watershed plans shall be accepted by the Board of Public Works and placed on file with the City Engineer. Maps showing these areas, when available, shall be posted on the City of Madison Website, https://www.cityofmadison.com/engineering/stormwater/. In the absence of a completed and accepted watershed plan for a watershed known to be experiencing flooding, new development or redevelopment shall comply with the requirements of Sec. 37.09(3)(c)2. and 3., as applicable. 5. Discharge Off-Site to Other Private Lands. When a site being reviewed by the Administrative Authority proposes to continue existing drainage patterns and discharge stormwater runoff onto property neither under the applicant's control (via ownership, easement or agreement) nor onto property under the control of the City of Madison, the Administrative Authority shall require the applicant to provide documentation that they have made significant efforts to obtain the right to discharge stormwater onto this property. If no such right can be obtained, the applicant shall be required to mitigate the increased volume of discharge on their property prior to making this discharge. Mitigation shall consist of implementation of a stormwater practice that shall match the existing volumetric discharges from the applicant's property to other lands not under their control in storm events including the 1-, 2-, 5- and 10-year storm events. If the proposed discharge is to an area that is an enclosed depression, this requirement shall be increased to include the 25- and 100-year storm events. (d) Outlets. Discharges from post-construction sites must have a stable outlet capable of carrying designed flow as required in Sec. 37.09(3)(c), at a non-erosive velocity. Outlet design must consider flow capacity and flow duration. This requirement applies to both the site outlet and the ultimate outlet to stormwater conveyance or water body. A minimum of 0.5' of freeboard shall be provided from the design peak elevation at the outlet of the basin compared to the elevation controls surrounding the basin (berms). (Am. by ORD-25-00017, 3-20-25, Eff. 4-1-25) (e) Infiltration. All plats, Certified Survey Maps, development, and redevelopment projects which create a cumulative total of twenty thousand (20,000) square feet or more of new impervious area since October 1, 2004 are required to provide infiltration of stormwater as set forth below. Stormwater management reports submitted to the City of Madison for review shall meet the requirements of Wis. Admin. Code ch. NR 151.12(5)(c). The stormwater management reports shall comply with the sections entitled "Criteria" within the applicable Infiltration Technical Standards as provided by the Department of Natural Resources and maintained by the Standards Oversight Council. A link to the technical standards is provided as follows: https://dnr.wi.gov/topic/stormwater/standards/postconst_standards.html. Stormwater infiltration shall comply with the following: 1. All Developments. Development applications received by the Planning Division shall be required to infiltrate sufficient runoff volume so that the post-development infiltration volume shall be at least ninety percent (90%) of the pre-development infiltration volume, based on an average annual rainfall, regardless of area necessary for this requirement. In accordance with Wisconsin DNR Post Construction Technical Standard 1002 (Site evaluation for stormwater infiltration), upon completion of site investigation (borings/pits) the infiltration system shall not be placed into amended or unamended loam (0.24 in/hr) or more restrictive soils if less restrictive unamended soils are readily available. Siting the location of the infiltration practices shall not interfere with other ordinances and pumping water shall not be required to meet this standard. Should the applicant prove to not be able to meet the infiltration requirement without dedicating more than two percent (2%) of the lot area for this purpose, they may optionally choose to meet the secondary recharge standard. (Am. by ORD-24-00066, 10-4-24, Eff. 4-1-25; Am. by ORD-25-00017, 3-20-25, Eff. 4-1-25) 2. Secondary Recharge Standard. If the infiltration standard cannot be met by the developer with dedication of two percent (2%) or less of the lot area, the developer may choose to design an infiltration system and pervious surfaces to meet or exceed the estimated average annual recharge rate as determined from the Wisconsin Geological and Natural History Survey's 2009 report, Groundwater Recharge in Dane County, Estimated by a GIS-Based Water Balanced Model or subsequent updates to this report, or by a site specific analysis using other appropriate techniques. If this alternative design approach is taken, at least two percent (2%) of the site area shall be dedicated as part of the effective infiltration area. (Am. by ORD-25-00017, 3-20-25, Eff. 4-1-25) 3. Distributed Best Management Practices. If the applicant proposes to use distributed practices (e.g. rain gardens) to meet infiltration requirements, a deed restriction and maintenance agreement will be required. These shall be recorded against individual parcels. (Am. by ORD-25-00017, 3-20-25, Eff. 4-1-25) 4. Pre-Treatment. Prior to infiltration of runoff from parking lots, new road construction (in commercial, industrial and institutional areas), the runoff shall be pre-treated. This pre-treatment shall be in accord with the applicable Standards Oversight Council Technical Standard. Infiltration systems designed in accordance with this section shall, to the extent technically and economically feasible, minimize the level of pollutants infiltrating to the groundwater and shall maintain compliance with the prevention action limits at a point of standards application in accordance with Wis. Admin. Code ch. NR 140 for all pollutants excepting chloride. Further, if site-specific information indicates that compliance with the applicable prevention action limit is not achievable, the infiltration device shall not be installed or shall be modified to prevent infiltration to the maximum extent practicable. 5. Prohibitions. Notwithstanding paragraphs 1 through 4, infiltration systems shall not be installed in any of the following areas: a. Areas associated with Tier 1 industrial facilities as identified in Wis. Admin. Code ch. NR 216.21(2)(a). b. Storage and loading areas of Tier 2 industrial facilities as identified in Wis. Admin. Code ch. NR 216.21(2)(b). c. Fueling and vehicle maintenance areas. 6. Exemptions. Runoff from the following areas may be credited toward meeting the requirement for infiltration under Sec. 37.09(3)(e) when it is infiltrated. However any requirement for infiltration of runoff from these areas is optional: a. Parking areas and access roads less than five thousand (5,000) square feet for commercial development. b. Parking areas and access roads less than five thousand (5,000) square feet for industrial developments not subject to paragraph 5. above. c. Redevelopment sites, unless previous development of the site required infiltration. d. Roads in commercial, industrial and institutional land uses, and arterial residential roads. e. Areas where the infiltration rate of the soil is less than 0.60 inches per hour measured at the bottom of the proposed infiltration system, provided that, based on test pits, a more permeable soil layer with infiltration rates exceeding 0.60 inches per hour does not exist within two (2) feet of the proposed bottom of the infiltration device. 7. Location of Practices. Infiltration practices shall not be located in the following areas: a. Areas with less than five (5) feet of separation distance from the bottom of the infiltration system to the elevation of the seasonal high groundwater or the top of bedrock for Industrial, Commercial, Institutional parking lots and roads, and for residential arterial roads. b. Areas with less than three (3) feet of separation distance from the bottom of the infiltration system to the elevation of the seasonal high groundwater or the top of bedrock for all other source areas not identified in a. above. c. Areas with less than one (1) foot of separation distance from the bottom of the infiltration practice to the elevation of the seasonal high groundwater or top of bedrock for roofs draining to subsurface drainage systems. d. Areas where infiltrated water will contain runoff from commercial, industrial, or institutional land uses or regional infiltration devices serving residential development, where the proposed infiltration device is within four hundred (400) feet of a community water system well as specified in Wis. Admin. Code ch. NR 811.16(4). e. Areas where contaminants of concern, as defined in Wis. Admin. Code ch. NR 720.03(2), are present in the soil through which infiltration will occur. 8. Alternative Uses. Where alternate uses of runoff are employed, such as for toilet flushing, laundry or irrigation, such alternate use shall be given equal credit toward the infiltration volume required by this section. (f) Thermal Control. The stormwater management plan shall include provisions and practices to reduce the temperature of runoff for sites located within the watershed of a river or stream identified by the Wisconsin Department of Natural Resources as a Cold Water Community. For the City of Madison, these watersheds include the Badger Mill Creek (Upper and Lower) and Door Creek. Meeting the infiltration standards of Sec. 37.09(3)(e), MGO, shall satisfy all requirements for thermal control. If a site is exempt or excluded from infiltration requirements but is located in a thermal control watershed, the thermal requirements of this section apply and shall be met. (g) Protective Areas. Impervious surfaces shall be kept out of the protective areas to the maximum extent practicable. The stormwater management report shall contain a written site-specific explanation for any parts of the protective area that are disturbed. Where land disturbance occurs within the protective area and where no impervious surface is present, adequate sod or self-sustaining vegetative cover of seventy percent (70%) (of the disturbed area) or greater shall be established and maintained. Best management practices may be located within protective areas. 1. For outstanding resources waters and exceptional resources waters and for wetlands in areas of special natural resource interest as specified in Wis. Admin. Code ch. NR 103.04 — the protective distance is seventy-five (75) feet. 2. For perennial and intermittent streams identified on a United States Geological Survey 7.5 minute series topographic map, or on a county soil survey map, which is more current — the protective distance is fifty (50) feet. 3. For lakes — the protective distance is fifty (50) feet. 4. For highly susceptible wetlands — the protective distance is seventy-five (75) feet. Highly susceptible wetlands include the following: calcareous fens, sedge meadows, open and coniferous bogs, low prairies, coniferous swamps, lowland hardwood swamps and ephemeral ponds. 5. For less susceptible wetlands — the protective distance is ten percent (10%) of the average wetland width, but not less than ten (10) feet nor more than thirty (30) feet. 6. For wetlands not subject to paragraphs 4. or 5. above, the distance shall be fifty (50) feet. 7. For concentrated flow channels with drainage areas greater than one hundred thirty (130) acres — the protective distance is ten (10) feet. 8. Redevelopment post-construction sites are exempt from the protective area requirements. 9. Structures that cross or access surface waters are exempt from the protective area requirements. (h) CARPC Requirements. Where, as a condition of approval of an urban service area extension, the Capital Area Regional Plan Commission (CARPC) requires compliance with additional stormwater management standards, the applicant shall comply with the resolution of approval for this urban service area as issued by CARPC and approved by the Wisconsin Department of Natural Resources (WDNR) and/or the Madison Metropolitan Sewerage District (MMSD). (4) Stormwater Management Goals. (a) For existing development, implement practices to reduce by twenty percent (20%) the anticipated total suspended solids entering waters of the state, as compared to no controls, by March 10, 2007 and a forty percent (40%) reduction by March 10, 2011. This as designed/modeled standard will be met on a municipality wide basis. In the event that the majority of the communities in the Madison Lakes watershed fail to adopt similar provisions, then the requirements of this section shall revert to those contained in Wis. Admin. Code ch. NR 151.13(2). (b) For street reconstruction, the following shall apply: 1. Total Suspended Solids (TSS) Control — Reduce, to the maximum extent practicable, total suspended solids loads leaving the site by forty percent (40%), based on average rainfall, as compared to no runoff management controls. This method requires the use of a continuous model such as SLAMM or P8, and of approved grain size distribution curves and rainfall data. These files are managed and maintained by the Wisconsin Department of Natural Resources and are available on its website. No person shall be required to exceed forty percent (40%) total suspended solids reduction to meet the requirements of this subdivision. This analysis shall use approved procedures and assume no re-suspension of particles. This analysis shall require tracking of the particulate sizes trapped by each device used in series (or treatment train). Serial redundant removal efficiencies shall not be allowed. For example, a catch basin and an inlet filter, each being approximately twenty-five percent (25%) effective, do not provide a fifty percent (50%) removal efficiency. Rather, as these devices both trap the same particle size the combined efficiency of these two (2) devices used in series remains at twenty-five percent (25%). 2. Infiltration — design practices to infiltrate stormwater runoff from the roadway in accordance with Wis. Admin. Code ch. NR 151.24(5). 3. Peak Discharge — design practice to reduce peak runoff from the roadway in accordance with Wis. Admin. Code ch. NR 151.24(4). (5) Off-Site Stormwater Management. Off-site stormwater management is allowed, provided that all of the following conditions for the off-site facility are met: (a) The facility is in place; (b) The facility is designed and adequately sized to provide a level of stormwater management that at least meets the ordinance standards; (c) The facility has a legally obligated entity responsible for its long-term operation and maintenance. (6) Installation Certification. Each applicant who is granted a stormwater management permit, and who has signed and recorded the required maintenance agreement, shall submit to the City Engineer certification that the BMPs referred to in the stormwater management report have been installed in accord with the plans and specifications of that report. This certification shall be provided and sealed by a Professional Engineer currently licensed in the State of Wisconsin, on forms available from the City of Madison Engineer. The City of Madison stormwater management permit shall not be closed without submission of this certification. This certification shall serve as Official Notice of Termination by the Applicant with regard to the stormwater management permit, and shall trigger a final site inspection by City Engineering staff. Upon completion of this inspection, a notice of permit closure and reminder to the Applicant of the annual stormwater management report requirement shall be sent and the stormwater management permit shall be closed. (7) Annual Stormwater Management Report. Each applicant who is granted a stormwater management permit, and who has signed and recorded the required maintenance agreement, shall submit to the City Engineer an annual report on the condition of the site's stormwater management devices. The annual report shall include the following: (a) Documentation of the completion of the required annual maintenance, including copies of receipts (actual prices paid need not be reported) from agents hired to perform the work and the date the work was completed; (b) Photos of the management device at the time of inspection. This shall include photos of existing conditions and photos after the completion of any required maintenance. This report shall be submitted by June 1 of each year following closure of the Stormwater Management Permit required under Sec. 37.09(6). The annual report shall be completed and sealed by a Professional Engineer currently licensed in the State of Wisconsin, on forms provided by the City Engineer. The requirement that the annual report be sealed by a Professional Engineer may be omitted in the case of a stormwater management plan consisting solely of storm sewer inlet filters, catchbasin sumps, or underground tanks, provided that the applicant can provide the appropriate documentation and dated photos as outlined in Secs. 37.09(7)(a) and (b). For sites with more extensive stormwater management systems, the Administrative Authority may allow other appropriately credentialed professionals to complete this work at their discretion. For sites that have a stormwater management device (or devices) that require a topographic survey every three years, this survey requirement may be satisfied through the submittal of adequate photographic documentation. The acceptance of date stamped photographs in lieu of a topographic survey is at the discretion of the Administrative Authority. The topographic survey requirement waiver may only be applied to qualifying detention or infiltration basins. For sites that have a stormwater management device (or devices) that infiltrate stormwater, the inspection shall be completed between 24-72 hours after a rainfall event > ½ inch to ensure it is draining down appropriately. Copy of a weather report with rainfall amount shall be included in the inspection report.
(Am. by ORD-25-00017, 3-20-25, Eff. 4-1-25) (Am. by ORD-25-00017, 3-20-25, Eff. 4-1-25) (Am. by ORD-25-00017, 3-20-25, Eff. 4-1-25) (Cr. by ORD-20-00051, 6-10-20)
Ask a question about Madison law
Corpus searches the Madison sections it holds and shows the ones that match, with their citations. Free, no sign-in.