17.10.420 - Single family residences - Special geologic hazard study area.
The construction of one single family residence per lot in the special geologic hazard study area shall be allowed, without the requirement for a regional study pursuant to Part 6 of this chapter, if a geologic hazard clearance for the construction has been issued by the director pursuant to Part 5 or renewed pursuant to Section 17.10.325 and all of the following criteria are met:
A. No zoning change or further subdivision or lot line adjustment is required to accommodate the construction of the single family residence.
B. All public or private infrastructure needed to support the residence has already been constructed, excluding storm and sanitary sewer laterals and utility service connections. Except for the construction of storm and sanitary sewer laterals and utility service connections, no construction of any additional infrastructure shall be allowed.
C. The existing public storm drainage system has sufficient capacity, as determined by the director, to convey present and future storm water runoff.
D. The construction has been designed in a manner which, at a minimum:
1. Prevents any additional storm water runoff or drainage on site; and
2. Provides for the drainage of any storm water runoff or drainage from the structure, driveway or other paved surfaces directly into the public storm drainage system.
E. A grading plan in accordance with the grading ordinance has been approved by the director, which provides, at a minimum, for:
1. Balanced grading, unless the applicant has demonstrated, to the satisfaction of the director, that an imbalance would promote increased soil or slope stability; and
2. Retaining walls which are not a part of the structure and which do not exceed five feet in height; and
3. Soil cuts and fills, other than necessary for the foundation of the structure, which do not exceed five feet in depth, measured from the existing ground surface to the proposed ground surface; and
4. A subdrainage system satisfactory to the director; and
5. Erosion control measures deemed by the director to be appropriate for all graded areas and the time of year in which the grading is anticipated to occur; and
6. The minimum amount of grading necessary, as determined by the director, to:
a. Construct the residence and attendant hard surfaces, and
b. Provide for proper drainage, and
c. Provide for the remediation of identified on-site and off-site geologic hazards.
(Ords. 25015, 25159, 25710.)