§ 3.3.217 — PROMPT COMPLETION OF WORK
City Code of Colorado Springs, Colorado (2026 S-22: current through Ord. 26-47, passed August 25, 2026) · Colorado Springs City Code § 3.3.217
Corpus is an independent public-information project, not the official City of Colorado Springs website. Stable reference: corpuslaw.us/code/406ea234-afac-4661-aa0d-35465d9857c1
3.3.217: PROMPT COMPLETION OF WORK:
After an excavation is commenced, the excavator shall proceed with diligence, expedite all work covered by the excavation permit, promptly complete the work and restore the street and any traffic-control devices to their original condition, or as near as may be, so as not to obstruct the public place or travel more than is reasonably necessary. Adverse weather conditions shall be cause for reasonable delay in prompt completion of work. When traffic conditions, the safety or convenience of the traveling public or the public interest require that the excavation work be performed as emergency work, the City may include the requirement at the time the permit is granted that a crew and adequate facilities be employed by the excavator twenty four (24) hours a day so that the excavation work may be completed as soon as possible. (1968 Code §10-118; Ord. 74-56; Ord. 85-214; Ord. 01-42)
Ask a question about Colorado Springs law
Corpus searches the Colorado Springs sections it holds and shows the ones that match, with their citations. Free, no sign-in.