§ 12-25 — Issuance of permit
Code of Ordinances, City of Burlington, Vermont (Current through Ord. 8-3-26, passed August 3, 2026) · Burlington Code of Ordinances § 12-25
Corpus is an independent public-information project, not the official City of Burlington website. Stable reference: corpuslaw.us/code/41501190-5016-4387-8d50-1965b190d7c3
12-25 Issuance of permit.
If the electrical inspector finds that the work to be done would be in compliance with this chapter if done according to code and further determines that a permit is required, then she or he shall cause one to be issued to the applicant.
(Rev. Ords. 1962, § 824; Ord. of 10-27-03, eff. 11-26-03)
Ask a question about Burlington law