§ 1105.15 — Charge for extension of water mains

Columbus City Codes; partial (Supp. No. 86: codified through Ordinance No. 2063-2026, enacted July 2, 2026) · Columbus City Codes § 1105.15

Corpus is an independent public-information project, not the official City of Columbus website. Stable reference: corpuslaw.us/code/423e01a4-7e37-4fdf-b452-f326c6870f6e

1105.15 - Charge for extension of water mains.

(A) Contract Areas: (1) All water main extensions in areas having contract with the city for water service shall be installed and paid for as specified in the contract. (B) Noncontract Areas: (1) All water main extensions in areas having no contract with the city for water service shall be installed and paid for by the developer, applicants or political subdivision requesting such service at no expense to the city, regardless of the size of water main installed or length of extension. (2) The specifications and standards of construction for all water main extensions shall be approved by the Division of Water. (3) The size of all water mains shall be determined by the administrator of the Division of Water and shall be large enough not only to serve the areas under immediate consideration but also to serve areas which are likely to be developed and which would be served by the water main under construction. Unless otherwise required by the administrator of the Division of Water, no water main shall be smaller than six (6) inches nominal diameter. (4) All extensions of water mains shall include the installation of all taps, valves and fire hydrants. The number and location of fire hydrants shall be in accordance with standards established by the Columbus Division of Fire and shall be installed and paid for by the applicant or developer under the supervision of the Columbus Division of Fire. The number and location of all taps and valves shall be as required by the administrator of the Division of Water. (5) All water mains and appurtenances shall be owned, operated and maintained by the city, with title to be vested in the city upon completion of the water main. (C) Within the city. (1) All water main extensions in the city shall be paid for by the applicant or developer requesting such extension. Where a water main extension is required by the city to be installed larger than eight (8) inches in nominal diameter, the city shall pay one hundred ten (110) percent of the difference in the cost of the pipe, fittings and valves between the installation of an eight (8) inch water main and the water main installed. (2) The administrator of the Division of Water shall determine from the division's records, or other sources, the cost of the pipe, fittings and valves, and this determination shall be final. (3) The Director of Columbus Water & Power may authorize water main extensions to be installed by a qualified developer and the director shall determine whether the water main shall be installed by the city or by the applicant or developer. (4) For each water main extension requested and installed by the city, the Division of Water shall make an estimate of the total costs involved and the applicants or developer shall make a deposit to the city that is sufficient to cover the estimated cost of the water main extension. If the actual cost of the extension is higher or lower than the deposit, the applicants or developer will be refunded the amount of any excess deposit or shall pay to the city any deficit that may exist in the deposit, as the case may be. (5) When water main extensions are installed by the city, the cost may be assessed against the abutting property owners, with the approval of council. Such assessment shall be in an amount equal to the total installation cost unless the line is required by the city to be larger than eight (8) inches. When the water main is required by the city to be installed larger than eight (8) inches, the amount assessed shall be the total installation cost less one hundred ten (110) percent of the difference in the cost of the pipes, fittings and valves between the installation of an eight (8) inch watermain and the water main installed. The costs shall be determined as prescribed in paragraph (2) above. (6) The specifications and standards of construction for all water main extensions shall be prepared by the Division of Water. Plans and installation shall be subject to approval of the Division of Water. (7) The size of all water mains shall be determined by the administrator of the Division of Water and shall be large enough not only to serve the areas under immediate consideration but also to serve areas which are likely to be developed and which should be served by the water main under consideration. Unless otherwise required by the administrator of the Division of Water, no water main shall be smaller than six (6) inches nominal diameter. (8) All extensions of water mains shall include the installation of all taps, valves and fire hydrants. The number and location of the fire hydrants shall be in accordance with the requirements of the Columbus Division of Fire. The number and location of all taps and valves shall be as required by the administrator of the Division of Water. (9) All water mains and appurtenances shall be owned, operated and maintained by the city, with title to be vested in the city upon completion of the water main. (10) No water mains shall be installed except by the city unless authorized by an agreement between the city and the developer or applicants. Where water mains are installed by a developer or applicants and abut on parcels not owned by the developer or applicants nor included in the agreement, the developer or applicants shall be entitled to reimbursement when such parcels are connected to the water main within ten (10) years after the completion of the water main from the funds collected by the city for such connections pursuant to Section 1105-11 C.C. The amount of the reimbursement shall be determined by dividing the cost of the water main paid by the developer or applicants by the available frontage abutting on the water main provided that the total amount of reimbursement per front foot of property served shall not exceed the applicable charges established by Section 1105.11 C.C. To be eligible for this reimbursement, the developer or applicants must file with the Division of Water within ninety (90) days after the completion of the water main or such further time as may be authorized by the Director of Columbus Water & Power in accordance with the standards and specifications, receipts for all labor and material used in connection with the construction of the water main, together with the final, as-built plans, properly referenced for future location of the work.

(Ord. 478-92; Ord. 422-06 § 2 (part); Ord. No. 0971-2010, § 1, 9-13-2010; Ord. No. 0139-2011, § 1, 3-7-2011; Ord. No. 2398-2012, § 4, 12-3-2012; Ord. No. 1163-2015, § 1, 5-18-2015; Ord. No. 1882-2026, § 1, 6-29-2026)

Ask a question about Columbus law

Corpus searches the Columbus sections it holds and shows the ones that match, with their citations. Free, no sign-in.