Sec. 42-301. - Requirements for stormwater management plan approval.
(a) Stormwater management plan required for all developments. No application for development will be approved unless it includes a stormwater management plan detailing in concept how runoff and associated water quality impacts resulting from the development will be controlled or managed. This plan must indicate whether stormwater will be managed on-site or off-site and, if on-site, the general location and type of practices.
The stormwater management plan(s) shall be referred for comment to all other interested agencies, and any comments must be addressed in a final stormwater management plan. This final plan must be signed by a licensed professional engineer (PE), who will verify that the design of all stormwater management practices meet the submittal requirements outlined in the submittal checklist found in the Stormwater Design Manual. No building, grading, or sediment control permit shall be issued until a satisfactory final stormwater management plan, or a waiver thereof, shall have undergone a review and been approved by the AEA after determining that the plan or waiver is consistent with the requirements of this article.
(b) Final stormwater management plan requirements. A final stormwater management plan must be submitted for approval. The final stormwater management plan shall include all of the information required in the final stormwater management plan checklist found in the Stormwater Design Manual. This includes:
(1) Contact information. The name, address, and telephone number of all persons having a legal interest in the property and the tax reference number and parcel number of the property or properties affected.
(2) Topographic base map. A 1" = 200' topographic base map of the site which extends a minimum of 200 feet beyond the limits of the proposed development and indicates existing surface water drainage including streams, ponds, culverts, ditches, and wetlands; current land use including all existing structures; locations of utilities, roads, and easements; and significant natural and manmade features not otherwise shown.
(3) Calculations. Hydrologic and hydraulic design calculations for the pre-development and post-development conditions for the design storms specified in this article. Such calculations shall include: (i) description of the design storm frequency, intensity and duration, (ii) time of concentration, (iii) soil curve numbers or runoff coefficients, (iv) peak runoff rates and total runoff volumes for each watershed area, (v) infiltration rates, where applicable, (vi) culvert capacities, (vii) flow velocities, (viii) data on the increase in rate and volume of runoff for the design storms referenced in the Stormwater Design Manual, and (ix) documentation of sources for all computation methods and field test results.
(4) Soils information. If a stormwater management control measure depends on the hydrologic properties of soils (e.g., infiltration basins), then a soils report shall be submitted. The soils report shall be based on on-site boring logs or soil pit profiles. The number and location of required soil borings or soil pits shall be determined based on what is needed to determine the suitability and distribution of soil types present at the location of the control measure.
(5) Maintenance covenant. The design and planning of all stormwater management facilities shall include detailed maintenance and repair procedures to ensure their continued function. These plans will identify the parts or components of a stormwater management facility that need to be maintained and the equipment and skills or training necessary. Provisions for the periodic review and evaluation of the effectiveness of the maintenance program and the need for revisions or additional maintenance procedures shall be included in the plan. The maintenance covenant must also comply with sections 42-247 and 42-323 of this article.
(6) Landscaping plan. The applicant must present a detailed plan for management of vegetation at the site after construction is finished, including who will be responsible for the maintenance of vegetation at the site and what practices will be employed to ensure that adequate vegetative cover is preserved. This plan must be prepared by a registered landscape architect or a professional engineer licensed in the State of Mississippi.
(7) Erosion and sediment control plan. The applicant shall submit an erosion and sediment control plan which shall include:
a. A sequence of construction of the development site, including stripping and clearing, rough grading, construction of utilities, infrastructure, and buildings, and final grading and landscaping. Sequencing shall identify the expected date on which clearing will begin, the estimated duration of exposure of cleared areas, and the sequence of clearing, installation of temporary erosion and sediment measures, and establishment of permanent vegetation.
b. All erosion and sediment control measures necessary to meet the objectives of this local regulation throughout all phases of construction and permanently, after completion of development of the site. Depending upon the complexity of the project, the drafting of intermediate plans may be required at the close of each season.
c. Seeding of mixtures and rates, types of sod, method of seedbed preparation, expected seeding dates, type and rate of lime and fertilizer application, and kind and quantity of mulching for both temporary and permanent vegetative control measures.
d. Modifications to the plan:
(i) Major amendments of the erosion and sediment control plan shall be submitted to the AEA and shall be processed and approved, or disapproved, in the same manner as the original plans.
(ii) Field modifications of a minor nature may be authorized by the AEA by written authorization to the permittee.
(8) Other environmental permits. The applicant shall assure that all other applicable environmental permits have been acquired for the site prior to approval of the final stormwater design plan.
(9) Preconstruction site checklist. The applicant shall submit the preconstruction site checklist provided in Section 3.3.1 of the Stormwater Design Manual.
(Ord. of 1-21-2020(1))