Decommissioning plan required.
R.I. Gen. Laws § 39-35-2
in effect39-35-2. Decommissioning plan required.
The developer of any ground-mounted solar system shall, at the time they apply for
required permits from the municipality of jurisdiction, submit a plan for decommissioning
to include an estimate of the financial cost of implementing the plan. The municipality
shall be required to keep the decommissioning plan on file; provided that, doing so
does not make the municipality responsible for its implementation. Each municipality
may require the developer to post a performance bond to cover the cost of its decommissioning
plan.
P.L. 2024, ch. 380, § 1, effective January 1, 2025; P.L. 2024, ch. 381, § 1, effective
January 1, 2025.
Source: State of Rhode Island General Assembly (rilegislature.gov)URL: https://webserver.rilegislature.gov/Statutes/TITLE39/39-35/39-35-2.htmFetched: 10/20/2026