Sec. 12-22. - Applicability and administration.
This article applies to any request for demolition of residential and accessory structures within the territorial limits of the City of San Antonio that meets the criteria for deconstruction as established in this article.
(1) Criteria. Any application for demolition of a structure that is determined by the director to meet the criteria for deconstruction shall consider the construction date and original use of the structure. The director, at his or her discretion, may refer the applicability of criteria to a property to the historic and design review commission (HDRC) for a recommendation before a determination is made.
a. Construction date. The construction date of a structure shall be informed by available primary sources including, but not limited to Sanborn Maps, deed records, appraisal district data, and/or other applicable research methods.
b. Original use. The original use of the property shall be determined by the director after a visual assessment of construction type and reference to the 1968 city plan. The current zoning or use of the property does not determine whether the requirements of this section apply.
(2) Phasing. This article shall take effect in phases as set forth below.
a. Phase i shall take effect on October 1, 2022. Deconstruction requirements shall apply to demolition permit applications for city-executed demolitions for:
1. Residential single-family structures, multi-unit structures with four (4) units or less, and accessory structures that were constructed on or before December 31, 1920, regardless of zoning overlay; and
2. Residential single-family structures, multi-unit structures with four (4) units or less, and accessory structures that were constructed on or before December 31, 1945, and that have either: been locally designated as historic and carry a historic zoning overlay (H, HL, HS, or HE); or, are located within a Neighborhood Conservation District (NCD) and carry a NCD zoning overlay.
b. Phase II shall take effect on January 1, 2023. Deconstruction requirements shall apply to demolition permit applications for:
1. Residential single-family structures, multi-unit structures four (4) units or less, and accessory structures that were constructed on or before December 31, 1920, regardless of zoning overlay; and
2. Residential single-family structures, multi-unit structures four (4) units or less, and accessory structures that were constructed on or before December 31, 1945, and that have either: been locally designated as historic and carry a historic zoning overlay (H, HL, HS, or HE); or, are located within a Neighborhood Conservation District (NCD) and carry a NCD zoning overlay.
c. Phase III shall take effect on January 1, 2025. Deconstruction requirements shall apply to demolition permit applications for:
1. Residential single-family structures, multi-unit structures eight (8) units or less, and accessory structures that were constructed on or before December 31, 1945, regardless of zoning overlay; and
2. Residential single-family structures, multi-unit structures eight (8) units or less, and accessory structures that were constructed on or before December 31, 1960, and that have either: been locally designated as historic and carry a historic zoning overlay (H, HL, HS, or HE); or, that are located within a neighborhood conservation district (NCD) and carry a NCD zoning overlay.
(3) The director is authorized to administer and enforce the provisions of this article and adopt rules, procedures, and forms to implement the provisions of this article.
(4) The director may temporarily suspend or modify the requirements of this article based on a determination that such requirements are temporarily infeasible due to economic or technical circumstances. The director shall temporarily suspend the requirements of this article if, at any time, there are less than three (3) certified deconstruction contractors registered with the city.
(Ord. No. 2022-09-08-0668, § 1, 9-8-22)