Section 13.03.1320 Equipment Installation Deadlines
Unless a shorter time is ordered by the Wastewater Director, users required to install flow monitoring and sampling equipment must complete installation within one hundred eighty days of notification to install the equipment or the department may do so, with or without further notice, at the user’s sole expense and liability.
Date Passed: Monday, December 8, 2025 Effective Date: Sunday, January 18, 2026 ORD C36776 Section 87